Page 1

FEDERAL BUDGET 2025-26

2025-26 2027-28 GOVERNMENT OF PAKISTAN FINANCE DIVISION ISLAMABAD

Page 3

Preface

This document has been prepared to comply with the requirement laid down in Section 9 of Public Finance Management Act, 2019. The medium-term Performance Based Budget which is referred to as the "Green Book" is an endeavor to specify the purposes i.e. outputs and outcomes expected to be achieved with funds appropriated by the National Assembly. The Green Book provides supplementary information to the details of Demands for Grants and Appropriations, which set out the details of the Budget by accounting Budget line according to the functional and object classifications of the Chart of Accounts. The key elements of Green Book are:

Three-year framework for budgetary planning which lies at the heart of the Medium- Term Budgetary Framework (MTBF) reforms. Under this process Principal Accounting Officers (PAOs) make their plans and prepare budgetary estimates for a rolling 3-year budgetary horizon. This includes the 2025-26 estimates, which are to be appropriated by The National Assembly, and two outer years’ estimates FYs 2026-27 and 2027-28 for planning purposes.

Breakdown of each PAO’s Budget by "Outputs". Each PAO identifies its main lines of service delivery and the costs associated with the delivery of each service, down to the level of the individual spending unit. This would enable National Assembly and other stakeholders to assess whether value for money in terms of delivery of services is being achieved.

Linkage of service delivery with total budgetary allocations for each PAO (current and development). As the government budget is divided between the recurrent budget and development budget, the delivery of outputs and outcomes requires combine allocation of recurrent and development budget to access the services or improvement of the future quality of public services.

Development of indicators, which should be used for measuring the quantity and quality of services (outputs) to be delivered. The Green Book also provides targets for the levels of services, which the PAOs are expecting to achieve. Budgetary preparation based on specified outputs/services, provides a basis for monitoring of the results expected from public spending.

Identification of outcomes that represent effects of service delivery on the target population. Outcomes are often more difficult to measure than outputs and are typically measured less frequently. I hope that this document would be of value in terms of describing the linkage between budgetary allocations and the public services delivered.

IMDAD ULLAH BOSAL

Secretary to the Government of Pakistan

Finance Division Islamabad, the 10th June, 2025

Page 5

Table of Contents

Cabinet Division................................................................................................................................. 1
President’s Secretariat- Personal......................................................................................................... 3
President’s Secretariat - Public........................................................................................................... 3
Prime Minister’s Office-Public.............................................................................................................. 4
Prime Minister Office-Internal.............................................................................................................. 5
National Disaster Management Authority.............................................................................................. 6
Board of Investment........................................................................................................................... 7
Naya Pakistan Housing Development Authority.................................................................................. 11
Pakistan Atomic Energy Commission................................................................................................. 17
Pakistan Nuclear Regulatory Authority............................................................................................... 19
Pakistan Space and Upper Atmosphere Research Commission........................................................... 21
Establishment Division...................................................................................................................... 25
Federal Public Service Commission................................................................................................... 30
National School of Public Policy........................................................................................................ 31
Civil Services Academy.................................................................................................................... 32
National Security Division................................................................................................................. 33
Special Technology Zones Authority.................................................................................................. 35
Intelligence Bureau (IB).................................................................................................................... 37
Council of Common Interests............................................................................................................ 38
Climate Change and Environmental Coordination Division................................................................... 39
Commerce Division.......................................................................................................................... 43
Communications Division.................................................................................................................. 46
Defense Division.............................................................................................................................. 49
Survey of Pakistan......................................................................................................................... 52
Defense Production Division............................................................................................................. 53
Power Division................................................................................................................................. 57
Petroleum Division........................................................................................................................... 60
Federal Education and Professional Training Division......................................................................... 63
Higher Education Commission.......................................................................................................... 80
National Vocational and Technical Training Commission..................................................................... 84
National Heritage and Culture Division............................................................................................... 87
National Rehmatul-lil Aalameen Authority........................................................................................... 91
Page 6

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Finance Division.............................................................................................................................. 93
Auditor General of Pakistan............................................................................................................ 100
Revenue Division / Federal Board of Revenue.................................................................................. 102
Foreign Affairs Division................................................................................................................... 107
Housing And Works Division........................................................................................................... 109
Human Rights Division................................................................................................................... 111
National Commission of Human Rights............................................................................................ 114
National Commission on the Status of Women, Islamabad................................................................ 115
National Commission on the rights of Child....................................................................................... 117
Industries and Production Division................................................................................................... 118
Information and Broadcasting Division............................................................................................. 121
Information Technology and Telecommunication Division.................................................................. 127
Interior and Narcotics Control Divsion.............................................................................................. 132
National Counter Terrorism Authority............................................................................................... 136
Kashmir Affairs and Gilgit Baltistan Division...................................................................................... 140
Law and Justice Division................................................................................................................. 142
Supreme Court of Pakistan:............................................................................................................ 146
Islamabad High Court..................................................................................................................... 147
National Accountability Bureau........................................................................................................ 150
Federal Ombudsman Secretariat for Protection Against Harassment.................................................. 151
Election Commission of Pakistan..................................................................................................... 153
Council of Islamic Ideology............................................................................................................. 154
Federal Judicial Academy............................................................................................................... 155
Federal Tax Ombudsman Secretariat............................................................................................... 160
Wafaqi Mohtasib Secretariat........................................................................................................... 161
Maritimes Affair Division:................................................................................................................ 162
Narcotics Control Division, Islamabad.............................................................................................. 164
National Food Security and Research Division, Islamabad................................................................. 166
National Health Services, Regulations and Coordination, Islamabad................................................... 169
Overseas Pakistanis and Humans Resources Development, Islamabad............................................. 173
Parliamentary Affairs, Islamabad..................................................................................................... 176
Planning Development and Special Initiatives Division, Islamabad..................................................... 178
Pakistan Agriculture Research Council............................................................................................. 188
Poverty Alleviation & Social Safety Division...................................................................................... 189
Benazir Income Support Programme, Islamabad.............................................................................. 191
Page 7

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Pakistan Bait ul Mal:....................................................................................................................... 193
Privatization Division:..................................................................................................................... 196
Railways Division:.......................................................................................................................... 203
Religious Affairs and Inter-faith Harmony:......................................................................................... 206
Science and Technology Division:................................................................................................... 209
States & Frontier Region Division.................................................................................................... 216
Water Resources Division:.............................................................................................................. 218
The Senate:................................................................................................................................... 222
National Anti-Money Laundering and Counter................................................................................... 223
Special Investment Facilitation Council............................................................................................ 224
Cannabis Control Regulatory Authority............................................................................................. 226
Page 9

Cabinet Division

PAO: Cabinet Secretary

1. Goal: The pivotal secretarial setup of the Federation of the Islamic Republic of Pakistan and symbolizes the mode of dispensation of the executive authority of the State under the Constitution and the Rules of Business framed there under.

2. Policy: Federal Ministers and Ministers of State (salaries, allowances and privileges) Act, 1975, Policy / Rules for Monetization of Transport Facility for Civil Servants, Honors and Awards Policy, Toshakhana Policy, Observance of Annual Principal of Policy etc.

3. Outcomes: 4. Budget by Outputs: Rs. In 000’

Outputs Office Actual Expenditure Budget Medium Term Budget
Responsible 2023-24 2024-25 2025-26 2026-27 2027-28
Policy formulation and implementation Cabinet Division/ Admin Wing 1,810,499 2,834,929 3,635,698 3,118,686 3,118,686
Emergency relief assistance / operation Emergency Relief Wing 959,296 1,039,342 3,026,814 975,988 975,988
Preservation of State Documents Organization wing 178,698 264,777 411,000 157,350 157,350
Government administrative reforms Institutional Reforms Cell 19,609 44,000 76,000 48,365 48,365
Security of classified communications NTISB Wing 193,762 193,877 350,000 213,563 213,563
Regulatory Services RA Wing 201,468 306,493 311,000 336,364 336,364
Community Development Service Development Wing 10,370,000 75,000,000 70,000,000
Promotion of tourism Org Wing 330,947 124,000 224,000 136,565 136,565
Centralize supply of Forms / Gazettes Org Wing 41,753 40,000 47,000 44,022 44,022
Total 14,106,032 79,847,418 78,081,512 5,030,903 5,030,903
Page 10

5. Key Performance Indicators/Targets

Outputs Key Performance Indicators Delivered Target 2023-24 Planned Target 2024-25 Medium Term 2025-26 2026-27 Target 2027-28
Policy formulation & Implementation Awards (Number of awards) 716 200 200 220 240
Emergency relief assistance / operation Flying in Hours 716 1200(Hours) 1200 (Hours) 1200 (Hours) 1200 (Hours)
Preservation of state documents Archive papers digitized (number of papers) 65,000 50,000 50,000 50,000 50,000
Restoration of deteriorated archive documents (number of documents) 4100 3,500 10,000 10,000 12,000
Documents Preserved-cabinet Record (number of documents) 32,405 31,880 31,880 31,880 31,880
Microfilming rolls documents digitized (number of microfilms) 45,000 50,000 50,000 55,000 60,000
No. of exhibition of Photographs and rare documents depicting our freedom struggle will be mount on National Days 05 6 6 6 6
Promotion of tourism Guidance provided to foreign tourist (number of foreign tourist) 40,000 40,000 40,000 50,000 60,000
Guidance provided to local tourist (number of local tourist) 15,000 16,000 16,000 18,000 20,000
World Tourism Day Workshop Organized (No of workshops) 02 2 2 2 2
Holding events workshop with different stakeholders including private sector stakeholders 06 14 14 15 16
Guidance to tourists through social media & Tourism web site (No of tourists visited websites & followers on social media platform 1,732,388 4,000,000 4,000,000 4,500,000 5,000,000
Page 11

President’s Secretariat- Personal

PAO: Military Secretary to the President

1. Goal: Efficient and smooth functioning of President’s Secretariat (Personal)

2. Policy: 3. Outcomes: Improved Governance

4. Budget by Outputs: Rs. In 000’

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Administrative Services 76,257 124,710 212,710 235,000 322,000
Staff and Household Services ’ 559,616 693,562 987,393 995,000 1,050,000
Estate Gardens establishment Services Presidents Secretariat Pl 51,988 63,330 105,180 130,000 150,000
Travelling & conveyance services (ersona) 118,854 475,750 376,450 495,000 525,200
Health Services for President Secretariat 33,596 60,150 78,050 90,000 99,000
Total 840,311 1,417,502 1,759,783 1,558,492 1,558,492

President’s Secretariat - Public

PAO: Secretary to the President

Rs. In 000’

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Facilitation in Smooth functioning of President of President’s Secretariat (Public) 596,037 946,603 933,746 996,299 1,058,966
Pakistan as the Head of State
Total **596,037 ** 862,603 933,746 901,611 901,611
Page 12

Prime Minister’s Office-Public

PAO: Secretary to the Prime Minister

1. Goal: Prime Minister Office (Public) processes all cases requiring the decision of the Honorable Prime Minister.

2. Policy: Rules of Business. 1973 (As amended till 14th September 2021)

3. Outcome: Timely execution of all summaries/references/cases requiring decision of the Prime Minister and ensuring implementation of PM’s Directives.

4. Budget by Outputs: Rs. In ‘000

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Administrative Services PM’s Office Public 674,341 860,520 896,542 922,213 950,000
Total 674,341 860,520 896,542 922,213 950,000

5. Key Performance Indicators/Targets:

Outputs Key Performance Target Achieved Planned Target Medium Term Target
Indicators 2023-24 2024-25 2025-26 2026-27 2027-28
Administrative Services Timely execution of all summaries/references/cases requiring decision of the Prime Minister 100 % Achieved As Per direction of Prime Minister As Per direction of Prime Minister As Per direction of Prime Minister As Per direction of Prime Minister
To implement the Prime Minister’s Directives 100 % Achieved As Per direction of Prime Minister As Per direction of Prime Minister As Per direction of Prime Minister As Per direction of Prime Minister
Page 13

Prime Minister Office-Internal

PAO: Military Secretary to the Prime Minister

1. Goal: To facilitate Honorable Prime Minister of Pakistan in discharging of his duties

2. Policy: To ensure efficient & smooth running of official business of Honorable Prime Minister of Pakistan

3. Outcomes: As Above

4. Budget by Outputs: Rs. In 000’

Output Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Administrative Services 563,124 656,669 697,569 705,298 730,643
Reception Services 3,383 4,030 4,236 4,568 4,865
Estate Gardens Establishment Services Prime Minister’s Office (Internal) 31,842 36,824 44,875 44,272 47,275
Travel and 53,903 82,420 96,577 103,813 110,316
Conveyance Services
Health Services 7,983 13,799 14,464 15,506 16,476
Total 660,235 793,742 857,721 873,457 909,575
Page 14

National Disaster Management Authority

PAO: Chairman

1. Goal: To ensure safety and sustainability of Human Lives during a Natural Disaster through effective operational relief & Rescue activity. To prepare in advance against disaster to avoid human and infrastructure losses through a strengthening DRR mechanism.

2. Policy: National Disaster Management Plan (NDMP) Disaster Risk Reduction (DRR)

3. Outcomes: Due to policy intervention loss in terms of Human Lives and infrastructure was minimum during flood-2022

4. Budget by Outputs Rs. In 000’

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
To cope with disaster at the local and national level through coordination and capacity building of sub- national and international disaster management authorities, Creation of DRR awareness & making DRR part of Government plan and policies. Disaster Risk Reduction (DRR) 697,611 822,979 908,293 905,683 905,683
Total 697,611 822,979 863,786 905,683 905,683
Page 15

Board of Investment

PAO: Secretary

1. Goal: Promoting domestic and foreign investment to enhance Pakistan's economic development. Increase in investment to GDP ratio.

2. Policy:

  • I. Investment Policy 2013

  • II. Foreign Direct Investment Strategy 2013-17

  • III. Special Export Zones Act 2012

  • IV. Special Export Zones Rules 2013

3. Outcomes: 4. Budget by Outputs: Rs. In ‘000

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Investment advisory and facilitation services Board of Investment 591,966 2,929,635 1,911,613 848,188 848,188
Total 591,966 2,929,635 1,911,613 848,188 848,188

5. Key Performance Indicators/Targets:

Outputs Key Performance Indicators Target Achieved 2023-24 Planned Target 2024-25 Medium Term Target 2025-26 2026-27 2027-28
Investment advisory Investment Promotion Strategy 2024-27 Under Process 12 Months 12 Months 12 Months 12 Months
and facilitation investment policy 2023 Delivered and Achieved 12 Months 12 Months 12 Months 12 Months
services Formulation of model BIT in consultation with stakeholders Delivered and Achieved 2 4 4 6
Review of Bilateral Investment Treaty (BIT) on the basis of New Model Negotiations with Mauritius, Iran,Qatar, Azerbaijan. Australia underway 2 2 3 3
Finalization of MOUs MoU with JETRO Japan, Energy Ministry of UAE concluded 6 6 4 4
Negotiations of Bilateral Investment Treaty (BIT) with foreign countries MoU with JETRO Japan, Energy Ministry of UAE concluded. 12 Months 12 Months 12 Months 12 Months
"Conferences & Seminars (Nos) 18 4 6 8 8
Page 16

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

(International / Local)" Reduction in time taken to issue process permissions to companies to open branch/liaison office. In Process 07 weeks 07 weeks 07 weeks 07 weeks
Grant permission to foreign companies to open branch/liaison office 201 270 500 600 650
Recommendation of Work Visas to expatriates working foreign and local companies in Pakistan. 4071 3580 4500 4500 5000
Holding of JWG Meeting 1 1 1 2 2
Participation in JCC Meeting 1 1 1 1 1
Holding of local conferences/seminars for CPEC advocacy and SEZ Promotions 0 1 1 1 1
Holding of international
roadshows/seminars/conferences for CPEC advocacy 1 4 4 4 4
Sectoral research studies for CPEC 0 0 1 1 1
Meetings of Pak-China Business & Investment Forum Steering Committee 0 0 1 2 2
Signing of MoUs/Agreement with China under CPEC Industrial Cooperation 7 3 2 2 2
Pak-China B2B JV facilitation 30 30 2 2 2
Diagnostic Studies by Chinese Experts 0 0 1 1 1
Capacity building programmes in China for CPEC related workforce 1 1 1 1 1
Grant of status of Special Economic Zone (SEZ) 8 0 5 7 7
SEZ Committee Meeting for SEZs Status 47 69 50 50 50
Integration of SEZ-MIS with PSW In process In process Completion 0 0
Feasibility Study and Acquisition of Land for the Establishment of ISLAMABAD MODEL SPECIAL ECONOMIC ZONE (IM-SEZ) In process In process Completion 0 0
Feasibility study and purchase of land for establishment of China Pakistan Economic Corridor Business & Industrial Cooperation Tower, Islamabad. In process Completion 0 0
Establishment of One Stop Service for SEZs In process In process In process Completion 0
Identification of Land for Establishment of Large Scale SEZ In process In process Completion 0 0
Simplification of SEZ MIS Module In process In process Completion 0 0
Business Process Mapping of Seven Priority (Automotive, Tourism & Hospitality, Logistics, Textile, Agri Businesses & food Pharmaceutical) 340 RLCOs have been mapped at Federal level in these priority sectors Completion 0 0 0
Page 17

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Hackathon held with public and private stakeholders aimed at formulating high impact regulatory reforms in key economic sectors Out of 32 reforms, 7 have been implemented, 10 are under implementation and 15 are under consultation Round II of Hackathon 0 0 0
Public Private Dialogues (PPD’s) held in 3 priority sectors (IT/ICT, Agri business and Food Processing, Tourism and Hospitality Out of 30 reforms 5 have been implemented, 5 are under implementation and 16 are under consultation Round II of PPDs 0 0 0
Meeting held in December 2023 in Lahore and in Januray, 2024 in Islamabad with all provincial and regional focal departments aimed at Cross fertilization and knowledge sharing. 280 total reforms (40 each) across seven regions. Out of 280, 132 reforms have been successfully implemented. 59 reforms are currently in progress. Phase-II 0 0 0
Capacity Building workshop held at Lahore and Peshawar. It is an ongoing activity workshops in other regions are planned in 3rd quarter of 2024-2025 Capacity Building Workshops Phase-II 0
Formulation of sectoral profiles (live Documents) of eight priority sectors (Automotive, Tourisms & Hospitality, Logistics, Textile, Agri Businesses & Food Processing, IT/ICT, Pharmaceutical Housing & Construction Sectoral profiles of priority sectors have been formulated and updated. These are live documents and facts and figures will be updated when and where required. Updating facts and figures/key information 0 0 0
Page 18

Prime Minister’s Inspection Commission PAO: Chairman

1. Goal: The Commission shall if so, directed by the Prime Minister to carry out the inspections and may

conduct inquiries in respect of any Ministry/Division/Department/Office/Corporation and

employees on various charges/allegations and any other assignment given by the Prime Minister.

2. Policy: Martial Law Order No. 58 of 1978

3. Outcomes: 4. Budget by Outputs Rs. In ‘000

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
To Observe/ensure transparency in Ministry / Prime Minister's Inspection Commission 122,598 146,904 153,039 164,472 180,920
Division/Department (PMIC)
Total 122,598 146,904 153,039 164,472 180,920

5. Key Performance Indicators/Targets

Outputs Key Performance Idit Target Achieved Planned Target Medium Term Target
ncaors 2023-24 2024-25 2025-26 2026-27 2027-28
To Observe/ensure transparency in Ministry / As per direction of prime Minister 100% achieved As per direction of Prime As per direction of Prime As per direction of Prime As per direction of Prime Minister
Division/Department Minister Minister Minister
Page 19

Naya Pakistan Housing Development Authority PAO: Chairman

1. Goal: To meet overall mission of NAPHDA i.e., Planning, Development, Construction and management of real estate development schemes and projects with particular focus on social and affordable housing and to empower low- and middle-income segments of the society.

2. Policy: To carry forward programs and initiatives undertaken by NAPHDA, including demand estimates, facilitation of

  • mortgage facility, incentivizing housing related business and creating employment opportunity in the society.

3. Outcomes: Ownership of decent housing to low-income segments of the society as well as improvement in the overall economy.

4. Budget by Outputs Rs. In ‘000

Output Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
To facilitate the Low-Income Segment for availing Housing NAPHDA Head Office 536,214 1,564,215 1,587,567 597,847 621,503
Total 536,214 1,564,215 1,587,567 597,847 621,503

5. Key Performance Indicators/Targets:

Key Performance Target Achieved Planned Targets Medium Term Target
Indicators 2023-24 2024-25 2025-26 2026-27 2027-28
Demand Assessment • Data of NAPHDA applicants from Registration Phase-1 was received from NADRA in both hard and soft formats. Subsequently, the hard copy forms were verified for accuracy • Applicants data segregated district wise • Engaging NADRA for comprehensive data profiling, structured as follows: a. Gender-based classification b. Marital status, including divorced and widowed applicants c. Identification of applicants with disabilities d. Classification of transgender individuals e. Data categorization of families and next of kin (NOK) of martyrs Aims at enhancing data accuracy and support targeted policy interventions New Registrations if & when required New Registrations if & when required
Page 20
• Future registration and processing of the cases through Online Portal
Signing of agreement with Govt entities Signing of under process 4x Agreements
Disbursement of Cost Subsidy Rs. 34.8 Mn released for PHA-KP Jalozai
Disbursement of loan under GMSS •Loans worth Rs 241 Bn approved for 61,532 x applicants •Rs. 120 Bn disbursed under GMSS
Housing Units financed under GMSS 31,391 HUs
Housing Units constructed / under construction in collaboration with public entities 116 HUs completed and handed over to allottees at PHA Jalozai-KP • 9204 HUs under construction in collaboration with CDA, LDA & PHA. • 839 HUs under construction in Peri-Urban areas of Punjab.
Creation of jobs 2,499,966
Structural Reforms • Constituted Committee on formulation of Slum Regeneration Regulations • Constituted Knowledge and Skills Evaluation Committee
Incentivizing Builders for investment in Construction Industry • Formulating and developing a comprehensive working paper aimed at facilitating private investors through targeted incentives to stimulate growth
Page 21
in the construction industry
Reforms for smooth functioning of the authority • Formulation of SOPs:- a. Governing Assets, its Capitalization, Depreciation, Transfer/ Relocation, Physical Verification and Coding & Tagging. b. Governing receipts, storage, handling, issuance and valuation of inventories. c. Internal Controls/ Utilization of Imprest (Petty Cash). d. Usage of Fleet/ Corporate Cards. e. Submission and Scrutiny of the Medical Claims. • E office system has been implemented since 30 September 2024 • HRM application, Inventory Management System, Digitization of complaints data and Mail tracking application have been deployed • Disposal of Surplus Unserviceable • Framing of NAPHDA Financial Regulations • Framing of NAPHDA Service Regulations for Permanent Employment • Framing of JV Regulations • Resumption of MPMG Scheme • Launching of E- Commerce platform for construction material • Amendment proposed for Regeneration of kachi abadis in provinces
Page 22
and Obsolete Assests
Regulating Agri Land & its conversion into Housing Societies in Pakistan Conducted an analytic review of Urban Expansion, water usage and corresponding Agricultural Land depletion Compiling measures for Agri- land conversion & its submission to IPC
Measures for removal of structural impediments in construction Industry • Working with Task Force on Housing and Construction Development • Devising a methodology to cater the issues and promotion of housing and construction sector. • Evolving strategies for removal of impediments in construction industry • Identify challenges and propose the growth framework for development and promotion of Housing Sector to the Task Force for approval and implementation.
Revision of Housing Policy - 2001 Drafted TORs for hiring consultant and submitted to M/o Housing & Works Areas / clauses Identification for revision
Assistance to NDMA Strategy formulation for resettlement of flood affectees
Page 23

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Formulation of 13thFive Year Plan relating to Physical planning & Housing • Devised detailed five year plan with corresponding strategies and actions for intervention • Submission of consolidated reports to Planning Commission
Capacity Building • Knowledge and Skills Evaluation Committee carried out training need assessment of employees and progress made by each individual is recorded in “Individual Training Score Card”. • In pursuance to professional excellence, total 331 NAPHDA Officers / Officials, have been trained. • Imparting Training to entire NAPHDA staff in office record & management. • Enhancing Staff skills in PPRA Rules & EPADs • Training in Accounting Imparted training to staff in IT related skills Ongoing training for NAPHDA officials and officers to ensure alignment with newly developed methodologies and evolving professional standards. Ongoing training for NAPHDA officials and officers to ensure alignment with newly developed methodologies and evolving professional standards.
Periodic skills evaluation of staff Conducted different tests against the trainings offered. The result remained at 95%. Conduct of tests to evaluate staff professional skills for training need assessments and efforts in hand to achieve over 95% results.
Complaint redressal • Established dedicated e-complaints portal. • Digitization of NAPHDA complaints data • Launching of e- complaints portal • Optimizing complainants’ satisfaction Optimizing complainants’ satisfaction
Improvement in members selection / registration • Amendments in prioritization criteria for selection of
Page 24
members / applicants • Procuring family registration certificate, from departments for processing of LCUs allotment • Reverification of survey of NADRA verified applicants.
Monitoring of ongoing Projects • Monitoring / visits/ inspections of ongoing Peri- urban schemes • Monitoring / visits/ inspections of Housing Scheme with LDA • Monitoring of Project with PHA-KP • Monitoring of project with CDA • Monitoring / visits/ inspections of ongoing Peri- urban schemes • Monitoring / visits/ inspections of Housing Scheme with LDA • Monitoring of Project with PHA- KP • Monitoring of project with CDA • Monitoring / visits/ inspections of Housing Scheme with LDA • Monitoring of Project with PHA-KP • Monitoring / visits/ inspections of Housing Scheme with LDA • Monitoring of Project with PHA-KP
Collaboration with other entities • Collaboration with CDA for Govt land identification for launching housing schemes. • Visits of Govt land indicated by CDA & Federal land for launching housing schemes Collaboration with following DAs for launching housing schemes. • Hyderabad DA • SBBHC • QDA • PHA-F • FGEHA Framing of modalities for launching projects in collaboration, independently or otherwise for 10,000 LCUs. Commencement of works on mutually agreed projects
Working on PPP Scheme • Pursuing GMSS reinstatement • Negotiation with Banks for housing finance • Negotiation with eligible developers for amendment in project financing mechanism • Negotiation with DAs for approval / services • Commencement of work provided GMSS as well as other financial modalities are finalized. • Handing over of 955 LCUs • Completion of CDA Farash Town Project (2,000 LCUs) Commencement of work and its monitoring Commencement of work and its monitoring
Page 25

Pakistan Atomic Energy Commission

PAO: Chairman

1. Goal: Research & Development through Energy & Social Sector

2. Policy: Peaceful, safe, reliable, economical, and secure application of nuclear science and technology for sustainable socio-economic development including Health Sector, Energy Sector, Education Sector and Bio-medical Sector

3. Outcomes: Impact on Target Population

  • I. Awareness, Improved life quality

  • II. Cost effective inputs etc.

  • III. Ultimately benefit to overall society

4. Budget by Outputs Rs. In ‘000

Output Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Administration Admin Division 8,111,249 4,965,296 2,268,419 2,379,119 2,379,119
Research, trainings and capacity building Nuclear Science Division 8,553,291 6,241,613 2,851,511 2,990,665 2,990,665
Food and Agriculture Development Nuclear Science Division 2,188,623 1,895,078 865,775 908,025 908,025
Public Health services and Development Nuclear Science Division 12,303,749 11,259,345 5,002,638 5,394,908 5,394,908
Minerals exploration, mining and development Fuel Sector 2,421,992 2,437,019 1,113,363 1,167,696 1,167,696
Power and fuel sector development Power Sector 10,596,149 17,468,089 8,741,380 8,369,823 8,369,823
Total 44,175,053 44,266,440 20,843,086 21,210,237 21,210,237

5. Key Performance Indicators/ Targets

Outputs Key Performance Idit Target Achieved Planned Target Medium Term Target
ncaors 2023-24 2024-25 2025-26 2026-27 2027-28
Research, trainings and capacity building MS-Nuclear Technology in PIEAS (Number of MS Fellows) 131 120 125 130 135
PhDs, M.Phil., MS/BS Engg. MSc (Number of students) 1808 1680 1660 1740 1820
Research Publications National/International (numbers) 448 320 330 340 350
Page 26

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Food and agriculture New Crops Variety produced (number of crop Varieties) 20 17 19 20 19
development Area of land in which control insect pest (Hector) 116,000 116,000 116,115 116,250 116,250
Training/workshop arranged (Number of trainings/workshops) 57 50 54 55 55
Number of PhDs, M.Phil., MS Scholars 260 200 200 200 200
Number of Research projects 81 90 90 90 92
Research publications national and international (numbers) 255 280 300 310 315
Public health services and development Patients to be treated through Nuclear Medicine and Oncology (Numbers) 1,267,373 915,000 1,000,000 1,100,000 1,150,000
Training Workshops arranged(Number) 167 150 140 130 130
Conferences/ Meetings (Number) 350 300 275 250 250
Research Projects (number of projects) 82 70 65 60 60
Power and fuel sector development Nuclear Power Plants Established (Number) 6 6 6 6 6
Installed Capacity of Nuclear Power Plants (MegaWatt) 3530 3530 Mwe 3530 Mwe 3530 Mwe 3530 Mwe
Page 27

Pakistan Nuclear Regulatory Authority

PAO: Chairman

1. Goal: Ensuring safety of Nuclear Installation and Radiation Facilities utilizing Nuclear Materials & Radiation sources in Industrial, Medical, Agriculture, Research & Development for protection of workers, public and environment from ionizing radiation.

2. Policy: PNRA ORDINANCE III OF 2001

3. Outcomes: Protection of workers, public & environment from ionizing radiation.

4. Budget by Outputs Rs. In ‘000

Output Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Development and maintenance of Regulatory Framework for Nuclear Installations & Radiation Facilitiesand their Authorization & Licensing, Review & Assessment, Inspection & Enforcement; Licensing ofOperating Personnel; Research & Development. Chairman Office 1,828,524 1,861,659 2,256,988 2,491,000 2,640,460
Capacity building of Pakistan Nuclear Regulatory Authority Chairman Office 149,557 256,330 - - -
Total 1,978,081 2,117,989 2,256,988 2,491,000 2,640,460

5. Key Performance Indicators/Targets:

Outputs Key Performance Indicators Target Achieved 2023-24 Planned Target 2024-25 Medium Term Target 2025-26 2026-27 2027-28
Development and maintenance of Regulatory Framework Development and Revision of Regulations and Regulatory Guides 6 5 7 4 6
for Nuclear Installations & Radiation Facilitiesand their Authorization & Licensing, Review & Assessment, Inspection Issuance/ Renewal of licenses to operating personnel of Nuclear Power Plants and Research Reactors 235 233 238 245 245
& Enforcement; Licensing ofOperating Personnel; Research & Development. Issuance / Renewal of Licenses to Nuclear Installations (Nuclear Power Plants, Research Reactors, RWMF, etc.) 22 28 31 32 33
Inspection of Nuclear Installations (Numbers) 1475 1648 1698 1705 1685
Issuance/ Renewal of 6573 7052 6657 6932 7112
Page 28
License for Radiation Facilities
Inspection of Radiation facilities (Numbers) 3202 3384 3221 3464 3594
Page 29

Pakistan Space and Upper Atmosphere Research Commission PAO: Chairman

1. Goal: To satiate Pakistan’s strategic and socio-economic developmental needs, SUPARCO is embarked on a comprehensive National Space Program (NSP 2047) catering all necessary elements including development of satellites, launch vehicle, launch facility, space science awareness and diverse space applications with an ultimate objective of achieving self-reliance / indigenous capabilities in the Space Science and Technology.

2. Policy: SUPARCO Approved Policy

The NSP-2047 is planned to be completed in two phases: (a) Phase-I (2017-30), (b) Phase-II (2031-47)

3. Outcomes: The envisaged outcomes of the NSP 2047 related programs and projects are to respond to national needs and concerns in terms of space applications, technology and disaster management. In Space Applications sector by utilizing data from remote sensing satellites reforms are expected in the sectors of agriculture, climate, urban planning, water resources, geology, disaster management etc. Earth observation will help in defence and national security domains. Further, own communication satellites provide services of telecommunication, TV broadcasting, cellular networking and internet services across Pakistan as well as South Asia, Middle East etc. and further DTH and SatComm services are soon to add. Through Navigation satellite program, SUPARCO aims to develop complete eco-system for its users that will consist of GNSS infrastructure, the technology and end-to-end solutions support. The Space Launch Facility and Space Launch Vehicle programs will enable the country to not only get independent access to space from the country but to also reduce / eventually eliminate the dependency on foreign resources thus saving precious national exchequer.

4. Budget by Outputs Rs. In ‘000

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Space and upper atmosphere research services Space and Upper Atmosphere Research Commission (SUPARCO) 9,219,801 36,604,084 - - -
Total 9,219,801 36,604,084 - - -

5. Key Performance Indicators/Targets

Outputs KPI’s Descrition Target Achieved Planned Target Medium Term Target
p 2023-24 2024-25 2025-26 2026-27 2027-28
Development & Deployment of Online Satellite Image Service (OSIS) Successful completion of the project and operationalization of the Online Satellite Image Service. Project has been successfully completed and available for the users. Completion of the project and operationalizatio n of the Online Satellite Image Service. Operationalizati on of the Online Satellite Image Service. Operation alization of the Online Satellite Image Service. Completion of procuremen ts, installation, commissioni ng • HR Induction • Establishme nt of Data Center and
Page 30
sharing / disseminatio n of imagery as well as derived products to customers all over in Pakistan
Advanced Systems for PakSat-1R Satellite Ground Control Segment (GCS) Completion of all planned procurement and System Integration. Operationalization of Advanced systems of PakSat-1R Satellite Ground Control Segment (GCS) All planned procurement and system integration has been completed after necessary inspection and testing. • System Integration Testing of all new and existing hardware to confirm synchronization Nil Nil . Procuremen t of Advanced Systems for PakSat-1R Satellite Ground Control Segment (GCS)
Pakistan Multi-Mission Satellite (PakSat-MM1**)** The launch of PakSat MM1 project intime and provision of planned services to its users. The target has been successfully achieved as PakSat-MM1 satellite has been successfully launched on 30 May 2024. Launch of Satellite Nil Nil • Critical Design Review (CDR) • Manufacturi ng of Satellite • Assembly, Integration and Testing
Establishment of Pakistan Space Center (PSC) Establishment of Space Center facility in time for indigenous development, testing, assembly and integration of satellites of planned capacity. Design of Technical Infrastructure and Facilities completed. • Design of Technical Infrastructure and Facilities • Manufacturing and Factory Acceptance of equipment/ machinery and subsequent Delivery at project site. • Training of manpower (Phase-I) • Constructi on of the Technical Building •Installatio n and Commissi oning of Technical Facilities/ Equipmen t • Training of Manpower (Phase-II) • Constructio n of Administrati ve and Security Infrastructur e • Scheme Design Review of Technical Infrastructur e and Facilities
Pakistan Optical Remote Sensing Satellite (PRSS-O2) The launch of PRSS O2 project in time and provision of planned services to its users. . Preliminary RFP floated to OEM . Confirmation of main PRSS-O2 • Request For Proposal (RFP) Floating for PRSS-O2 • Proposal by contractor •Contract • Design, Development and Manufacturing of PRSS-O2 System •Development • Launch and IOT Phase • Post Commissi on Phase • Design of Spectrometr y Laboratory • Design of Calibration and Validation
Page 31
specification received from OEM . Contract to be signed after approval of revised PC-I . Development of Calibration and Validation Facility under Capacity Building completed . Development of Spectrometry Lab under Capacity Building completed . Contract for Optical Payload AIT Equipment under Capacity Building placed Negotiations • Commencemen t of PRSS-O2 Contract (T0) • Kick off Meeting (KoM) • Development of Capacity Building Infrastructure of Capacity Building Infrastructure Site • Finalized equipment for Capacity Building
Initiation / Execution of development of Pakistan Communication Satellite - 2 (PakSat-2) Successful completion of the FSDS of PakSat - 2 • Consultant Hiring • Market Analysis • System Definition and Configuration Design Reports on definition and segmentation of relevant Satcom market and assessment of competitive environment have been prepared and are under review. . Local Consultant is • System Architecture Finalization • Business Plan and Marketing Strategy • PakSat 2 Satellite System Technical Documents Preparation • Preparation of final FSDS Report Nil Nil • Consultant Hiring • Market Analysis • System Definition and Configuratio n Design
Page 32
working on
development of business, marketing and sales plan for PakSat-2
system. . Working on
system architecture
finalization is underway
Page 33

Establishment Division

PAO: Secretary

1. Goal: Fostering excellence in the civil service by ensuring merit-based appointments, postings and promotions, capacity building through trainings, introduction of modern management techniques and technology, undertaking governance through institutions and systems and deconcentrating of power through effective decentralization

2. Policy:

  • Revision of policy for grant of BS21 and BS22 to Technical-Professional officers on account of Meritorious Services

  • Promotion policy grant of exemption from training

  • Inter provincial transfer policies.

  • Change in Rotation Policy for PAS / PSP

  • Change in promotion Policy-Forfeiture of Promotion rights by senior officers not availing nominations for mandatory training twice.

  • Civil Servant Act, 1973

3. Outcomes: 4. Budget by Outputs: Rs. In ‘000

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Policy formulation and implementation Establishment Division (Main), Human Resources Management Policy Reforms Cell, Staff Welfare Organization 2,220,105 3,544,521 4,014,564 4,005,904 4,068,988
Educational and Vocational Staff Welfare Organization 211,836 235,513 285,774 296,631 311,463
Pre and In-Service training of civil servants. Training infrastructure and management course development for civil servants Management Services Wing, Secretariat Training Institute 482,935 655,000 772,274 852,965 912,315
Research in Administrative Policies and Improvement in facilities provided to Civil Servants by the Federal Government Pakistan Public Administration Research Centre 133,602 161,000 166,885 205,017 235,769
Sports, Recreational and Cultural Staff Welfare Organization 167,787 159,642 179,405 204,427 214,648
Relief and Rehabilitation Staff Welfare Organization 17,958 34,000 40,500 37,800 39,690
Page 34

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Women Hostel and Day Care Centre Staff Welfare Organization 16,946 16,689 17,564 21,250 22,312
Financial Relief to incapacitated, retired employees and issuance of benevolent funds, marriage grants, farewell grants and educational stipends Board of Trustees, Federal Employees Benevolent & Group Insurance Fund 3,744,000 3,958,598 4,097,624 4,179,576 4,263,168
Rural Development support services Pakistan Academy for Rural Development & Akhtar Hameed Khan National Centre for Rural Development. 537,399 243,500 640,238 708,761 776,638
Total 7,532,568 9,008,463 10,214,828 10,512,331 10,845,001

5.Key Performance Indicators/Targets:

Outputs Key Performance Idit Targets Achieved Planned Targets Medium Term Targets
ncaors 2023-24 2024-25 2025-26 2026-27 2027-28
Educational and Vocational Number of beneficiaries for vocational trainings 2,177 2438 2560 2688 2822
Number of beneficiaries for educational stipends 23,830 17,259 18,122 19,028 19,979
Number of female dependents of the employees trained at Ladies Industrial Homes 1,999 2,301 2,416 2,536 2,663
Number of library memberships 2,336 2460, 2,583 2,712 2,848
Pre and In-Service training of civil servants. Training infrastructure and management course development for civil servants. Number of assignments completed by M.S. Wing including Management / Staff Periodic reviews and restructuring/ revamping of organization under the Federal government. 14 As per cases to be received.
Number of references for creation of posts dealt with. 98
Page 35

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Number of Status determination of organizations cases dealt with. Number of references regarding Job analysis / KPI exercise / special assignments dealt with. Number of references regarding Re-designation / upgradation of posts dealt with. 19 6 24
Number of cases related to devolution matters dealt with including court cases. 27
Number of Advices/views rendered on various miscellaneous issues. 63
Miscellaneous cases dealt with. 168
Number of training course organized. 1
Number of Officers trained during the Financial Year against the target thereof. 63
Matters relating to Surplus Pool dealt with. 803
Officers to be nominated in Service Training (MCMC, NMC & SMC) 732/994 1000 1,100 1,150 1,200
44TH STP 13 - - - -
SOPE - 2020 56 - 70 - -
51ST STP 0 31 - - -
52NDSTP 0 - 100 - -
STP 0 31 - - -
SOPE - 2021 0 - - - -
SDW (155 Courses) 1,812 1,401 2500 3000 3300
Research in Administrative A Guide to Performance Evaluation - - 1 - -
Policies and Secretariat Instructions 1 - - - -
Improvement in facilities provided to Establishment Manual - 1 - - -
Civil Servants by the Federal ESTACODE 1 - - - -
Government. A Manual on Staff Welfare Organization - 1 - - -
Page 36

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

A Manual on Benevolent Fund & Group Insurance - 1 - - -
A Manual on Travelling Allowance Rules - - 1 - -
A compendium of Laws & Rules Containing F&D Rules - - - - -
Common Services Manual Vol-I - - - 1 1
Printing of Organization & Functions of Federal Secretariat (Part-III) Revised Edition - - - - -
Printing of Organization & Functions of Federal Secretariat (Part-I) Revised Edition 1 - - - -
Idea Award Scheme - 1 - 1 -
Review & Revision of forms: i. "S" series forms (Regular Function). 1 1 1 1 1
ii. Weeding out of Redundant forms Exercise. - - 1 1 1
iii. ISO 9001:2015 of Establishment Division Quality objective of PPARC were updated Internal & External Audit would be conducted & minor observations, if any would be rectified Internal & External Audit would be conducted & minor observations, if any would be rectified Internal & External Audit would be conducted & minor observations , if any would be rectified Internal & External Audit would be conducted & minor observation s, if any would be rectified
Special Assignment: i. Observance and monitoring of 6% Balochistan Quota under AHBP 01 four Quarterly reports were prepared and forwarded to D.S. (IMP.) S&GAD, Balochistan 01 Four Quarterly reports 01 Four Quarterly reports 01 Four Quarterly reports 01 Four Quarterly reports
ii. Implementation Status of Resolution No.296 regarding verification of Balochistan domiciles. Continuous exercise, it would be co Committees of the ntinued till the further directions of National Assembly / Senate. the Standing
Page 37

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Triennial Census - - - - 2
Annual Statistical Bulletins 2 2 2 2 2
Receording / Indexing and Weeding out of old records. 04 Four Quarterly reports 04 Four Quarterly reports 04 Four Quarterly reports 04 Four Quarterly reports 04 Four Quarterly reports
Sports, Recreational and Cultural Number of community center memberships offered 4,589 3,449 3,622, 3,803 3,993
Sports, Recreational and Cultural Number of beneficiaries from Holiday Homes 1,471 2,2,06 2,316 2,432 2,554
Relief and Rehabilitation Number of beneficiaries for Relief Fund 1,772 1,352 1,420 1,491 1,566
Number of beneficiaries of Rehabilitation Aid 154 269 282 296 311
Number of beneficiaries of Ambulance / mortuary van and coaster service 1,014 1,755 1,842 1,934 2,031
Women Hostel and Day Care Centre Number of children availing day care facilities 14 19 20 21 22
Women Hostel and Day Care Centre Number of women to be accommodated in hostels 44 54 56 59 62
Financial Relief to incapacitated, retired employees and issuance of benevolent funds, marriage grants, farewell grants and educational stipends Number of beneficiaries (sum assured to the bereaved families of deceased employees) 47,604 52,483 55,108 55,863 58,656
Rural Development support services Number of officers to be trained under Pakistan Academy of Rural Development 725 850 900 900 900
Number of domestic training courses conducted by Akhtar Hameed Khan, NCRD. 38 40 40 40 40
Number of international training courses conducted by Akhtar Hameed Khan, NCRD. 2 2 2 2 2
Page 38

Federal Public Service Commission

PAO: Secretary

1. Goal: Merit based recruitment and selection of human resource for public sector

2. Policy: FPSC Ordinance, 1977

3. Outcomes: Impact on Target Population

4. Budget by Outputs: Rs. In ‘000

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Recruitment through FPSC 1,198,750 1,338,443 1,471,892 1,443,555 1,587,910
Competitive Exams & General Recruitment
Total 1,198,750 1,338,443 1,471,892 1,443,555 1,587,910

5. Key Performance Indicators/Targets:

Outputs Key Performance Idit Target Achieved Planned Target Medium Term Target
ncaors 2023-24 2024-25 2025-26 2026-27 2027-28
Recruitment through Framing of Recruitment Rules 40 65 70 72 75
Competitive Exams & General Recruitment Number of Allocations to be made through Central Superior Services 209 245 255 265 270
Exams, advice on recruitment rules for posts under No. of allocations to be made through general recruitment in BS-16-22 882 2050 2100 2150 2200
Federal Government and recommendation for merit-based selection No. of Exams to be conducted 22 15 15 15 15
Page 39

National School of Public Policy

PAO: Rector, National School of Public Policy

1. Goal: Perpetual quest towards attainment of improved governance, effective service delivery and effort to build capacity in Pakistan in the different areas of nation building, Governance & leadership, Economy, Security, Sustainable Energy, Education, Health and Stabilization.

2. Policy: National School of Public Policy Ordinance, 2002 (No.XCIX of 2002). NSPP (Amendment) Act, 2010 and NSPP Ordinance No. XCIX of 2002 (Amendment) 2017

3. Outcomes: Administrative Management Training of Civil Servants belonging to Federal/Provincial Government and Public Sector Organizations (BS-20, BS-19 & BS-18 Officers)

4. Budget by Outputs Rs. In ‘000

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Post induction- mandatory management trainings for civil servants National School of Public Policy (NSPP) 2,576,497 3,368,514 3,391,048 3,705,215 3,705,215
Total 2,576,497 3,368,514 3,391,048 3,705,215 3,705,215

5. Key Performance Indicators/Targets:

Outputs Key Performance Idit Target Achieved Planned Target Medium Term Target
ncaors 2023-24 2024-25 2025-26 2026-27 2027-28
Post induction- mandatory Number of officers to be trained in BS-20 103 100 100 100 100
management trainings for civil Number of officers to be trained in BS-19 324 350 350 350 350
servants Number of officers to be trained in BS-18 532 600 600 600 600
Page 40

Civil Services Academy

PAO: Director General, Civil Services Academy

1. Goal: To improve the quality and effectiveness of public policies and management in Pakistan by improving the quality of pre-service and in-service training and education of all those engaged in public service.

2. Policy: http://csa.gov.pk

3. Outcomes:

  • a. CTP: To organize pre-service common training programme for probationary officers in BS-17

  • b. STP: Specialized Training Programme for PAS Officers

  • c. MCMC: Mid Carrier Management Course for PAS Officers

4. Budget by Outputs: Rs. In 000’

Outputs Office Resonsible Actual Expenditure Budget Medium Term Budget
p 2023-24 2024-25 2025-26 2026-27 2027-28
Induction and Training of Occupational Groups Civil Services Academy, Lahore 1,202,530 1,825,243 2,000,283 1,897,923 1,897,923
Total 1,202,530 1,825,243 2,000,283 1,897,923 1,897,923

5. Key Performance Indicators/Targets

Outputs Key Performance Delivered Target Planned Target Medium Term Target
Indicators 2023-24 2024-25 2025-26 2026-27 2027-28
Induction and Training of Occupational Groups Number of Trainings to be conducted (CTP) 232 250 250 250 250
Number of Trainings to be conducted (STP) 36 50 50 50 50
Page 41

National Security Division

PAO: Secretary, National Security Division

1. Goal:
  • I. Implementation of National Security Policy approved in January 2022 in coordination with all the stakeholders. Ongoing process.

  • II. To enhance and institutionalize consensual decision on National Security issues and coordinate effective implementation.

2. Policy: www.nsd.gov.pk

3. Outcomes: 4. Budget by Outputs Rs. In ‘000

Output Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
A comprehensive National Security Policy. Collective thinking on key National Security Issues. Better informed public and key stake holders on National National Security Division 159,555 230,559 240,618 280,000 320,000
Security issues. Improved relation with counterpart agencies in other countries.
Total 159,555 230,559 240,618 280,000 320,000
5. Key Performance Indicators/Targets:
Outputs Key Performance Indicators Target Achieved 2023-24 Planned Target 2024-25 2025-26 Medium Term 2026-27 Target 2027-28
A comprehensive National Security Policy. Collective thinking on key National Security Formulation, approval and issuance of a comprehensive National Security Policy Achieved 100% As per req As per req As per req
issues. Better informed public and key stake Implementation of National Security Policy (2022-26) Achieved 45% As per req As per req As per req
holders on National Security Issues. Improved relation with counterpart Midterm review of National Security Policy Achieved 100% As per req As per req As per req
agencies in other countries. Establish an inclusive and broad-based post policy discourse in key areas of National Security Policy Achieved 100% As per req As per req As per req
Page 42

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Seminars/Conferences to explore ways and means of implementing issues raised in NSP midterm review Achieved 100% As per req As per req As per req
Maintain a minimum frequency of National Security Committee meetings Subject to convey of meeting by PM Subject to convey of meeting by PM Subject to convey of meeting by PM Subject to convey of meeting by PM
Establish the sub committee’s mechanism as an integral part of NSP Achieved 100% As per req As per req As per req
Policy Input on Traditional Security Achieved 100% As per req As per req As per req
Policy Input on Non- Traditional Security Achieved 100% As per req As per req As per req
Page 43

Special Technology Zones Authority

PAO: Chairperson, Special Technology Zones Authority

1. Goal: Streamline and harmonize legal and regulatory framework for STZA, enabling, promoting ease of doing business and establishment of STZA

2. Policy: Attract investment into zones including Foreign Direct Investments, venture capital funds, public sector investments, public-private investments and private funds

3. Outcomes: 4. Budget by Outputs Rs. In ‘000

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Effective Legal and Licensing Compliance Framework Developed and Implemented 51,878 45,018 68,423 50,855 55,940
Notification of Zones and Licensing of Zone Entities 118,748 52,521 76,128 59,330 65,264
Development and operationalization of Islamabad Technopolis (self-developed) 13,194 52,521 138,280 59,330 65,264
A digital portal for zone entities, integrated with other Government. Agencies for licensing operations and Management STZA 201,734 397,659 408,402 449,216 494,135
Operationalization of fiscal and monetary Incentives at Federal & Provincial Level 121,407 60,024 83,832 67,807 74,589
Strategic marketing and branding nationally and globally to attract investments through partnerships and Alliances 177,949 142,557 146,400 161,040 177,144
Total 684,910 750,301 921,465 847,578 932,336
5. Key Performance Indicators/Targets:
Outputs Key Performance Indicators Target Achieved 2023-24 Planned Target 2024-25 Medium Term Target 2025-26 2026-27 2027-28
Effective Legal and STZA Authority Regulations 100% 80% 100% - -
Licensing STZA free regulations 100% 80% 100% - -
Page 44

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Compliance Framework STZA Licensing Framework Regulations 100% 100% - - -
Developed and implemented STZA Monitoring and Evaluation Regulations 60% 100% - - -
STZA One window facility regulations 100% 100% - - -
STZA sanctions, fines and penalties regulations 60% 100% - - -
STZA Rules for Appellate Tribunals 80% 25% 100% - -
Amendments in STZA Rules - - 50% 100% -
Notification of Zones and Licensing of Zone Entities Number of special technology zones notified 11 10 12 14 17
Development and operationalization Development & Approval of Masterplan & Building Bylaws by CDA 100% 100% - - -
of Islamabad Technopolis (self- Developed) Provision of Utilities up to zero point and construction of Boundary Wall of Islamabad Techno polis 15% 35% 100% 100% 100%
Trunk Infrastructure Development for Islamabad Technopolis - 40% 100% - -
Development & Operationalization of O&M Framework for Islamabad Technopolis - 50% 100% - -
Islamabad Technopolis Land Allocation Legal Framework 100% 100% - - -
Operationalization of Islamabad Technopolis - - 30% 70% 100%
A digital portal for zone entities, Development of One window Portal Enterprise 100% 100% - - -
integrated with other Government Operationalization/Implementation of One Window Portal Enterprise 100% 25% 100% - -
Agencies for licensing operations and management Number of Service-Level Agreements with other Government Agencies 3 As per need As Per need As Per need -
Operationalization of fiscal and monetary Federal Incentives operationalized % (Dependency on Federal Government) 60% 60% 100% 100% -
incentives at Federal & Provincial Level Provincial Incentives operationalization % (Dependency on Provincial Government) 0% 30% 80% 100% 100%
Strategic marketing and branding nationally and globally to attract investments Investments committed for Islamabad Technopolis through applications 0 0 PKR 14B (USD 50M) PKR 28B (USD 100M) PKR 42B (USD 150M)
through partnerships and alliances Investments Projections submitted by other STZAs (PKR) PKR 49B PKR 65B PKR 105B PKR 104B PKR 175B
Page 45

Intelligence Bureau (IB)

PAO: Director General, Intelligence Bureau

1. Goal: Federal Intelligence / Reporting to Govt. on National Security

2. Policy: Define Policy Direction for Medium Term Years (Secret)

3. Outcome: Impact on Target Population (Federal Intelligence)

4. Budget by Outputs :

Rs. In ‘000

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Federal Intelligence Intelligence 13,382,285 18,324,914 19,120,993 20,159,731 20,159,731
Service Bureau
Total 13,382,285 18,324,914 19,120,993 **20,159,731 ** **20,159,731 **
Page 46

Council of Common Interests

PAO: Secretary

1. Goal: Formulation and Regulation of Policies in relation to matters in Federal Legislative List, Part-II. Safeguard the interests of Provinces and resolve Federal, Provincial and Inter-Provincial disputes.

2. Policy: Council of Common Interests, Compositions and Function, Rules of Procedure

3. Outcomes: Chairman i.e., Prime Minister of Pakistan may summon the meetings of the council. The Council shall meet at least once in ninety days. Provided that the chairman may convene a meeting on the request of a province on an urgent matter.

4. Budget by Outputs:

Output Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Formulation and Regulation of Policies in relation to matter in Federal Legislative List II CCI Secretariat 63,637 98,262 112,937 121,982 137,230
Total 63,637 98,262 112,937 121,982 137,230
5. Key Performance Indicators/ Targets
Outputs Key Performance Idit Target Achieved Planned Target Medium Term Target
ncaors 2023-24 2024-25 2025-26 2026-27 2027-28
Formulation and Regulation of Policies in relation to matter in Federal Legislative List Part- II and Coordination among Federal and Provincial Governments for Resolution of disputes on such matters. Chairman i.e Prime Minster of Pakistan may summon the meetings of the Council. The council shall meet at least once in ninety days. Provided that the Chairman may convene a meeting on the request of a province on an urgent matter. 2 (50%) 4 4 4 4
Page 47

Climate Change and Environmental Coordination Division

PAO : Secretary

1. Goal: To ensure that climate change is mainstreamed in the economically and socially vulnerable sectors of the economy and climate change performance index by 2026.

2. Policy: I. National Climate Change Policy II. National Environmental Policy III. National Sanitation Policy

IV. National Resettlement Policy V. National Drinking Water Policy VI. National Climate Change Act VII. National Forest Policy

VIII. National Hazardous Waste Management Policy.

3. Outcome: Improved Pakistan rating of greenhouse gas emissions by 2026 and Protection of

Environment, Energy and Conservation of Wildlife.

4. Budget by Outputs:

Outputs Office Actual Expenditure Budget Medium Term Budget
Responsible 2023-24 2024-25 2025-26 2026-27 2027-28
Environmental Protection, Conservation, Rehabilitation and improvement Services 10 billion Tree Tsunami Program, Pakistan Environmental Protection Agency 2,796,151 6,267,700 124,200 123,962 123,962
Conservation of Wildlife and Forest Services Zoological Survey of Pakistan 60,959 48,070 55,385 52,876 52,876
Research and Survey Services Global change impact study center 100,160 109,200 124,560 120,194 120,194
Policy making and administrative support Services Main Secretariat 386,488 782,056 701,087 748,290 748,290
Wildlife Management Services-ICT Islamabad wildlife Management Board 57,745 60,200 63,200 66,218 66,218
Formulate, Comprehensive adaptation and mitigation policies to address the effects of climate change Climate Change Authority - 150,000
Total 3,401,503 7,417,226 1,068,432 1,111,540 1,111,540
Page 48

5. Key Performance Indicators/Targets:

Outputs Key f Target Achieved Planned Target Medium Term Target
Perormance Indicators 2023-24 2024-25 2025-26 2026-27 2027-28
i. Environmental Protection of natural regeneration and 77.90 94.714 71.972 67.525
protection, conservation, reforestation through sowing/planting (in millions) Mill plants Mill plants Mill plants Mill plants
rehabilitation and improvement services Rehabilitation of Degraded Mountain Landscapes through community block plantations, farmers plantations and slope stabilization 39.563 Mill plants 48.047 Mill plants 36.511 Mill plants 34.255 Mill plants
Plantations through restocking of arable plantation, plantation on high lying areas and Afforestation in Irrigated Plantation 125.99 4.009 Mill plants 4.869 Mill plants 3.700 Mill plants 3.471 Mill plants
Rehabilitation of Riverine/Bela Forests Million plants 11.631 14.125 10.733 10.070
through planting/sowing Mill plants Mill plants Mill plants Mill plants
Assisted natural regeneration, Reforestation through sowing/planting and new afforestation 2.293 Mill plants 2.785 Mill plants 2.116 Mill plants 1.985 Mill plants
Road and canal side plantation through Restocking of degraded areas and new afforestation on blank areas 1.229 Mill plants 1.493 Mill plants 1.134 Mill plants 1.064 Mill plants
Compound of institutions, municipal and 0.367 0.446 0.339 0.318
park lands, avenue plantation Mill plants Mill plants Mill plants Mill plants
Block Plantations or Woodlots, shelter belts, agroforestry, saline and waterlogged plantations 3.277 Mill plants 3.980 Mill plants 3.024 Mill plants 2.838 Mill plants
Integrated watershed management (sub- valleys), Stream stabilization, Soil & water Conservation other than the watershed sites 5.006 Mill plants 6.079 Mill plants 4.620 Mill plants 4.334 Mill plants
Sustainable Use & Management of 0.395 0.480 0.364 0.342
Range lands-Pilot Project Mill plants Mill plants Mill plants Mill plants
Distribution of forest and fruit plants to govt and educational institutions, Pak army, local communities 81.491 Mill plants 98.965 Mill plants 75.203 Mill plants 70.556 Mill plants
Establishment of private and government nurseries (Bare rooted and tube plants) 117.127 Mill plants 142.244 Mill plants 108.090 Mill plants 101.411 Mill plants
IUCN Green Listingof National Parks - 1 No 2 No 2 No 1 No
Habitat mapping and assessment in the selected NPs (numbers) - 2 No 4 No 2 No 2 No
Baseline wildlife surveys - 1 No 2 No 2 No 2 No
Establish Protected Areas covering 37,007,6 sq km 109 No - - - -
Develop Management Plans for PAs 96 No - 1 No 1 No -
Breeding Centers 24 No - - - -
Community-developmentprojects 247 No - 4 No 2 No 2 No
Conservation fund - 25 No 25 No 50 No
Establish Check Posts to control illegal wildlife trade 40 No - - - -
Solid waste management in PAs 47 No - - - -
Establish Control Desks at Airports 5 No - - - -
Page 49

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Establish GIS Labs 9 No - - - -
GIS map of the selected NPs. - - 2 No 2 No 4 No
Capacity Building, Workshop & Trainings 167 No - 1 No 2 No 2 No
Engagement of local universities in wildlife based research - 3 No 6 No 6 No 5 No
Best practices case studies(numbers). - 1 No 2 No 3 No 2 No
Rehabilitation of sick and injured wildlife. - - 1 No 2 No 2 No
Average Air Quality Index of Pakistan (micro grams per cubic) meter ug/m3 of air 36.8 µg/m3 36.0 µg/m3 35.50 µg/m3 35.0 µg/m3 35.0 µg/m3
Air Monitoring Station(No) 2 2 3 4 4
Environmental Laboratories(No) 2 3 3 3 3
Environment Protection Tribunal(No) 1 1 1 1 1
ii. Conservation of Surveyof wild fauna(number) 11 11 12 12 12
wild life and forest services Studies on the population status of endangered and threaded species of wildlife. 2 2 3 3 3
Baseline studies of protected areas and important ecological zones. 2 3 4 4 3
National Conference on Endangered Wildlife of Pakistan (Number) - 1 1 0 1
Publications and Awareness 10 10 10 12 11
Maintenance, repairing and protection of Boundary Wall of Zoo-cum -Botanical Garden Islamabad. 1 1 1 1 1
iii. Research and Survey Services Dissemination of R&D findings research papers in International national Journalist & book (Nos) 17 24 24 24 25
Organization of Scientific Activities at International national journalist & book (Nos) 20 15 15 15 15
Technical Research Report(Nos) 10 12 12 12 15
Effort on capacity building of GCISC young scientists through academic and specialized trainings and participation conferences, workshops etc at international level (Nos) 25 25 30 30 30
Scientific Contribution Presentation in International Conferences and Workshops (Nos) 25 32 34 35 37
Scientific Contribution Presentation in National Conferences and Workshops (Nos) 48 50 52 52 55
Books, Monographs and published proceedings of important Conferences and Workshops (Nos) 10 12 12 12 15
Effort on capacity building of GCISC young scientists through academic and specialized trainings and participation conferences, workshops etc at National Level (Nos) 85 80 60 60 65
iv. Wildlife Management Training and capacity building of IWMB officers and staff national and international 1 8 10 12 14
Page 50

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Services-ICT Research on wildlife species of Margallah Hills National Park through camera trapping 4 12 14 16 18
Degraded patches declared as “Ecological Sensitive Area for Wildlife” in line with that declared a first “Leopard preserve Area” in Margalla Hills National Park 1 1 4 6 8
Develop a wildlife protection and conservation plan in Margallah Hills National Park ranges; - 6 6 6 7
Setup an entry points on Trial heads of Margallah Hills National Park - 6 6 6 8
Development of fire protection plan to prevent forest fire in Margallah Hills National Park and Development of Fire Control Room in Margallah Hills National Park - 1 1 1 1
Development of Margallah Wildlife Rescue Centre, Islamabad for Injured and orphan animals’ rehabilitation. Total wild animals rehabilitated and released. - 250 350 400 500
Formulate comprehensive Sectoral Provincial working groups (mitigation, adaptation, etc.) established. - - 4 4 4
adaptation and mitigation Sectoral Federal working groups (mitigation, adaptation, etc.) established. - - 4 4 4
policies to address the Annual Climate Report published. Donor conferences/meetings organized. - - 1 1 1
effects of climate change in Pakistan. Private sector entities engaged for Public-Private Partnerships (PPPs) on climate mitigation aspects. - - 2 2 2
Concept Notes developed for international funding. - - 3 5 8
PCCA Council meetings - 1 2 2 2
Page 51

Commerce Division

PAO: Secretary

1. Goal:
  • a. To promote, protect and expand international and national trade interests of Pakistan with a view to become a leading exporting country in the region. Increase in Trade to GDP ratio from 20% to 22%.

  • b. To sustain the growth of textile section and to keep domestic textile sector abreast of global competition and challenges.

2. Policy Documents:
  • i. Strategic Trade Policy Framework 2020-25 ii. National Tariff Policy iii. Textile Policy 2020-24

3. Outcome: To increase the volume of Pakistan’s export

4. Budget by Outputs Rs. In ‘000

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Administrative services Main Secretariat 1,132,164 1,848,934 1,718,180 2,035,518 2,035,518
Promotion of trade All Trade Missions, Pakistan Institute Trade & Development, Trade Dispute Resolution Organization, Trade Development Authority of Pakistan, Directorate General of Trade Organization and Liaison office Afghan Transit Trade Chaman 6,744,206 10,366,813 9,690,394 8,968,802 8,968,802
Rationalization of tariff and removal of tariff anomalies National Tariff Commission 406,384 425,000 520,000 467,899 467,899
Provision of Grant to Duty Drawback of Taxes (DLTL) Main Secretariat - 1,000,000 15,000,000 - -
To provide data bank and technical information to government as well as textile manufactures. Textile Commissioner’s Organization (TCO) 85,222 95,000 70,000 104,551 104,551
Provision of Subsidy of Import of Urea 6,000,000 - - - -
Total 14,367,976 13,735,747 26,998,574 11,576,770 11,576,770
Page 52

5. Key Performance Indicators/ Targets

Outputs Key Performance Indicators Target Achieved 2023-24 Planned Target 2024-25 Medium Term Target 2025-26 2026-27 2027-28
Administrative services Implementation of Strategic Trade Policy Framework (STPF) Strategic Trade Policy Framework (STPF) 2020-25 implemented. Textile and Apparel policy 2020- 25 approved by ECC. Strategic Trade Policy Framework (STPF) 2020-25 implemented. Textile and Apparel policy 2020- 25 approved. . Strategic Trade Policy Framework (STPF) 2025-30 implemented. Textile and Apparel policy 2020- 25 . Strategic Trade Policy Framework (STPF) 2025- 30 implemented. Textile and Apparel policy 2025-30 Implemented. . Strategic Trade Policy Framework (STPF) 2025- 30 implemented. Textile and Apparel policy 2025-30 Implemented.
Increase in value of textile export (US $ in million 16,656 19,184 19,370 21,420 23,740
Percentage increase in Exports 13.8% 8% 10% 11% 11.6%
Promotion of trade Increase in number of non-traditional products to be focused for export enhancement 10 Sectors 10 Sectors 10 Sectors 10 Sectors 10 Sectors
Total annual export of goods (US $ bn) 30.582 33.2 36.63 40.68 45.4
Specialized Training Programme (STP) (No. of participants) 8 8 10 10 10
Seminars and workshop held 140 150 150 150 150
Number of international trade exhibition undertaken by Trade Development Authority of Pakistan 112 124 153 160 165
Processing of fresh Licenses by DGTO to Trade bodies 52 55 62 60 60
Renewal of Licenses to the existing Trade Organizations and Chambers Grant of License 39 09 60 22 65 24 84 30 84 30
Page 53

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Rationalization of tariff and removal of tariff anomalies Number of advices to the Federal Govt. on Tariff and others trade measures (i) provide assistance to the domestic industry and (ii) improve the competitiveness of the domestic industry 381 4 7 9 10
Number of anti-dumping, Countervailing Duties and Safeguard cases resolved 32 12 16 18 18
Seminars and workshop held - 1 2 3 4
To provide data bank and technical information to government as well as textile manufactures. Amount of Textile Cess to be collected. (Rs.in million) 7.508 11.0 11.0 11.0 11.0
Page 54

Communications Division

PAO: Secretary

1. Goal: National cohesion and integration through development of sustainable communication infrastructure 2. Policy: Improvement of the socio-economic conditions of the people through development, expansion and maintenance of integrated roads networks

3. Outcome: Impact on Target Population - Construction & Transport Communications 4. Budget by Outputs: Rs. In ‘000

Outputs Office Actual Expenditure Budget Medium Term Budget
Responsible 2023-24 2024-25 2025-26 2026-27 2027-28
Policy formulation / revision and overall implementation services MoC, PME Cell, Postal wing 303,884 270,365 1,227,096 - -
Road infrastructure development, expansion and maintenance NHA (Current) 122,302,859 10,000.000 9,788,900 - -
Road safety on National Highways & Motorways Motorways Police 15,574,002 18,692,637 20,403,328 - -
Research and institutional development for the improvement of road transport and its management National Transport and Research Centre 125,461 218,374 249,267 212,981 212,981
Training services on the construction technology Construction technology training institute 435,135 410,759 452,328 - -
Provision of secure and time efficient postal services across the country PPOD 22,756,989 23,474,231 24,480,581 - -
Settlement of Insurance Claims - Legacy Portfolio PLIC 1,999,995 3,000,000 3,000,000 - -
Building and maintenance of National Highways and work on national Trade Corridor 227,751,533
Total 173,497,184 258,604,793 287,353,033 59,946,888 59,946,888
Page 55

5. Key Performance Indicators/Targets

Key Target Planned Medium Term Tar et
Outputs Performance Achieved Target
Indicators 2023-24 2024-25 2025-26 2026-27 2027-28
Road infrastructure development, expansion and maintenance Road maintenance (KMs) 11,200 13698 14480 1480 1480
Maintenance of KKH Thakot- Khunjrab road (kms) 615 615 615 615 615
Maintenance of KKH Skardu road (kms) 0 167 167 167 167
Building and maintenance of National Highways and work on national Trade Corridor Improvement and Rehabilitation of Roads as per national standards (KMs) 106 559 884 914 1496
Construction of Bridges (including interchanges and 2 1 3 5 3
underpasses)
NH&MP
Road safety on National Highways & Motorways Public Awareness Campaigns (No. of road users briefed/educated) (in million) 43.500 43.63 43.74 43.78 44.0
No. of employees/ persons to be trained in NH&MP 4297 1000 1100 1200 1300
No. of beats policed - 2 2 2 2
No. of helps rendered (in million) 2.380 2.61 2.62 2.63 2.64
Roads under policing jurisdiction of NH&MP (KMS) 4696 Existing =/4696 *New Roads = NIL Total=4696 6165 6440 6440 6440
NTRC
Collection of NTD IDO Data Collection NTD Collection NTD Collection NTD Collection NTD Collection NTD
129-Others Expenditure and capacity building 2-seminars 2-Training 3-Seminars 3-Trainings 4-Seminars 3-Trainings 2-Seminars 3-Trainings Collection 2-Seminars 3-Trainings
Development of Traffic Factors for Pakistan Research Study 0 15% 60% 25% 100%
Rural AccessibilityIndex Research Study 0 15% 60% 25% 100%
Page 56

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

of Pakistan
Analyzing Electric Vehicles (EV) Industry in Pakistan. Research Study 0 15% 60% 25% 100%
CTTI
Training services on the construction technology No of students to be enrolled in various disciplines 3239 6165 6440 6440 6440
PLIC
Settlement of insurance claims-legacy portfolio Insurance Claims Maturity 1,599,500 4,500,000 4,500,000 5,800,000 6,000,000
Insurance Claims- Death 125,100 800,000 900,000 1,000,000 1,000,000
Insurance Claims- surrender 317,500 1,200,000 1,000,000 1,000,000 1,000,000
Insurance Claims- Group life 250,000 2,500,000 2,000,000 1,000,000 1,000,000
Total 4,559,536 8,000,000 9,000,000 9,603,000 9,603,000
PPOD
Provision of secure and time efficient postal Revenue (In Billion) 9.256% 12.000 13.000 13.000 13.000
services across the country Public complaints settled (%) 98.99% 100% 100% 100% 100%
Speed of delivery (in Days) International Post (J means day of arrival at office of Exchange) 95% J+1 to J+6 J+1 to J+6 J+1 to J+6 J+1 to J+6
Speed of delivery ( In Days) Local Post (D means day of arrival at DMO of exchange 95% D+1 to D+6 D+1 to D+6 D+1 to D+6 D+1 to D+6
Payment made to Airlines (in Million) 626.4 990 1089 1197.9 1317.63
Number of Post Offices in Urban 2133 1823 1827 1830 1834
Number of post Offices in Rural 95% 8176 8180 8183 8186
Unregistered postal Traffic (in Milliion) - 137 140 145 150
Registered postal Traffic (in Million) 50.73 36 38 40 42
Page 57

Defense Division

PAO: Secretary

1. Goal: To defend national sovereignty and territorial integrity of Pakistan and to protect its national interest and assets

  • through military means.

2. Policy: 3. Outcomes: 4. Budget by Outputs Rs. In ‘000

Actual Budget Medium Term Budget
Outputs Office Expenditure
2023-24 2024-25 2025-26 2026-27 2027-28
Enforcement of national jurisdiction sovereignty in maritime zones Pak Maritime Security Agency 2,759,023 3,597,234 4,790,354 3,953,603 3,953,603
Defence Services Services HQs 1,865,441,456 2,122,000,000 2,550,000,000 - -
Topographical surveys, preparation of maps and demarcation of Pakistani borders Survey of Pakistan 2,507,269 2,499,603 10,669,070 3,068,880 3,498,523
School & college education services in Cantt Areas Federal Govt. Educational Institutions (Cantt / Garrison) 13,202,318 14,319,239 15,908,116 15,775,857 15,775,857
Administrative support to the Defence Forces and attached civil departments/policy making and coordination Defence Division (Main) 26,553,261 2,089,067 2,066,859 2,296,217 2,296,217
Provision for research and development (aerospace and cardiovascular) Defence Division (Main) 1,504,058 2,782,063 1,988,562 - -
Provision for development schemes (universities, educational institutes, cantonment development and defence complex) Development Wing 1,313,894 2,532,937 880,128 - -
Page 58

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Policy formulation and compliance of International Civil Aviation Organization (ICAO) standards Aviation Division 2,446,262 3,146,083 4,859,998 798,131 798,131
Provision of Meteorological expertise of Geo physical activities in the region Pakistan Meteorological Department 2,801,796 7,258,772 -
Provision of security to airports, aerodromes, aircrafts & civil aviation's installations and maintenance of law & order on airports Airports Security Force 13,627,228 19,035,538 17,566,415 15,846,220 15,846,220
Total 1,931,156,565 2,179,260,536 2,608,729,502 112,327,988 129,177,186

5. Key Performance Indicators/Targets:

Outputs Key Performance Indicators Targets Achieved 2023-24 Planned Target 2024-25 Medium Term Target 2025-26 2026-27 2027-28
Enforcement of national jurisdiction sovereignty in maritime zones Tolerance level for security lapses in maritime zones (Percentage) 100% 100% 100% 100% 100%
Number of sea hours on patrol in maritime zones Round the Clock Round the clock Round the clock Round the clock Round the clock
Topographical surveys, preparation of maps and demarcation of Pakistani borders Ground Verification of Sheets updated through IKONO MONO imaging (No. of Sheets) 200 sheets 200 sheets 200 sheets 200 sheets 200 sheets
Relocation / identification of international boundary pillars. Pak-India=63 Pak- Afghan=03 Total=66 80 pillars 80 pillars 80 pillars 80 pillars
Number of Inspection Standard Bench Mark throughout the country 500 - - - -
Page 59
Identification/ marking of pak Afghan border along wakhan corridor. 03 pillars 24 Pillars (Phase-III) _ - -
Federal Govt Educational Institutions (Cantt/ Garrison) Directorate Total number of students enrolled (Male/Female) 187233 Male:94359 Female:92874 183,478 M:92,350 F:91,128 183,693 M:92,353 F:91,340 183,913 M:92,474 F:91,438 183,913 M:92,474 F:91,438
Number of students per teacher (Male/Female) 25 per teacher 22 per teacher 22 per teacher 22 per teacher 22 per teacher
Total No. of teacher (Male/Female) 8327 Male:4550 Female:3778 8327 Male; 4550 Female; 3777 8327 Male; 4550 Female; 3777 8327 Male; 4550 Female; 3777 8327 Male; 4550 Female; 3777
Number of 3496 10,250 10,500 10,800 10,800
teachers to be trained (Male/Female) Male:1852 Female:1644 M:5,858 F:4,392 M:4,477 F:6,023 M:6,173 F:4,627 M:6,173 F:4,627
Number of students passed in first division (Male/Female) 14696 13,410 13,415 13,420 13,420
Number of seminars to be 49 14 14 14 14
conducted
Aviation Division
Provision of Accuracy of weather 9 >91% >92% >92% >92%
Meteorological forecast.
expertise and monitoring of Geo Accuracy of heavy rains and floods warnings. 3 >86% >87% >88% >88%
Physical activities in the region. Agro-Climatic Outlook for Rabi and Kharif Seasons 91.89% >85% >85% >85% >85%
Next 03 days Tehsil forecast for Potohar, Central/Eastern Punjab, Lower Khyber Pakhtunkhwa and Gilgit-Baltistan 87.02% > 90% > 90% > 90% > 90%
Weekly Tehsil Forecast for Punjab, K.P, G.B and Kashmir 86.35% > 85% > 85% > 85% > 85%
Impact Based Forecast (IBF) for Farmers of entire Potohar Region 91.02% > 85% > 85% > 85% > 85%
Weekly Tehsil Forecast for Sindh and Balochistan 82.69% >80% > 85% > 85% > 85%
Impact Based Forecast 83.05%
(IBF) for Farmers,
Page 60

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Chakwal and Attock Districts of Potohar Region
Provision of s to airports, aerodromes, & civil aviation installations a maintenance order on airpo ecurity aircrafts 's nd of law & rts Average time to resolve the issue Without Delay
No. of training of all cadres 29 ASF Academy 05 Foreign Course 20 Other Institutions 167 at Airports Total 221
No. of Joint Mock Exercises 25
No. of Quick Security Exercises 5200
No. of Security Audits 39
S urvey of Pakistan
Survey of Pakistan 2ndDigital Dataset on 1:50K scale 200 sheets 242 sheets 300 sheets 300 sheets 300 sheets
Relocation/Identification of International boundary pillars 66 80 pillars 80 pillars 80 pillars 80 pillars
Numb Bench countr er of Inspection of Standard mark (SBM) throughout the y. 500 500 500 - -
Thematic Map - 10 16 - -
District Map 70 70 70 70 -
General Map 61 50 50 50 50
Printing of sheets 120 200 200 200 200
Mapping of 36thParallel and above sheets - - 76 - -
Civil works for Geodetic datum - 70% 100% - -
Page 61

Defense Production Division

PAO: Secretary

1. Goal:

  • a) Self-Reliance through: -

  • i. Revitalization on Public Defense Industry.

  • ii. Growth of Private Defense Industry.

iii. Gradual Indigenization using Research & Develo9pment, Transfer of Technology, Offset, Human Resource Development etc.

b) Self-Sustenance through:

  • i. Enhancing Defense Export

  • ii. Corporatization

2. Policy: To develop a self-reliant and a self-sustained defense production industry along with increasing job opportunities, generation of revenue through taxes, decreasing dependence on imports and increasing the exports to earn foreign exchange.

3. Outcome: Transformation, Modernization and innovation of Defense Production and Ship building Industry leading to Self-reliance in defense sector of the county.

4. Budget by Outputs: Rs. In ‘000

Outputs Office Actual Expenditure Budget Medium Term Budget
Responsible 2023-24 2024-25 2025-26 2026-27 2027-28
Development of ship building industry in Pakistan for provision of ship-lift, repair and docking facilities to surface ships. Karachi Shipyard & Eng Works 2,560,862 3,776,000 1,786,000 - -
Administrative support to different entities of Ministry of Defense Production Ministry of Defense Production 1,196,162 1,094,950 1,093,054 - -
Total 3,757,024 4,870,950 2,879,054 - -

5. Key Performance Indicators/Targets:

Outputs Key performance Indicators Target Achieved 2023-24 Planned Target 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Administrative support to different entities Provision of ministerial support to DP Establishment based on TQM 75-85% 72-85% 75-80% 75-80% 75-80%
of Ministry of Defence production Exploring the potential of joint ventures with friendly foreign countries 70-75% 60-70% 70-75% 70-80% 70-80%
Timely completion of documentation involved in matters concerning foreign collaboration 70-75% 90% 100% - -
Page 62

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Development of ship building Infrastructure up-gradation Phase-I 82% - - - -
industry in Pakistan for Infrastructure Up-gradation phase-II 100% - - -
provision of ship repair and docking Activation of project Management cell Rawalpindi and Gwadar Offices 100% NA NA NA NA
facilities to surface ships. Office responsible Karachi Shipyard & Engineering works Acquisition of suitable land for construction of Shipyard Constructi- on 100% Design 55% KoM 20% NA 100% NA NA
Completion of Feasibility Studies NA NA 25% 50% 25%
Page 63

Economic Affairs Division

PAO: Secretary

1. Goal: Define Goal with Timeline Mobilization of foreign aid to achieve the development objectives in all sectors across the county.

2. Policy: 3. Outcomes: 4. Budget by Outputs Rs. In 000’

Outputs Office Actual Expenditure Budget Medium Term Budget
Responsible 2023-24 2024-25 2025-26 2026-27 2027-28
Foreign assistance, programming, negotiations, realization and management services and bilateral economic cooperation Policy and Admin Wing 800,713 905,153 943,571 1,016,401 1,118,041
Contribution to International Agencies Organizations for membership Policy Wing 14,887,049 24,611,115 16,280,690 17,908,759 19,699,635
Capacity Building of the Nationals of Friendly countries Economic Cooperation Wing 17,494 39,000 40,310 44,341 48,775
Support to Temporarily Displaced Persons- ERP TDP-ERP 1,800,283 5,125,000 3,400,000 - -
Foreign Debt Servicing Debt Management wing 1,020,401,885 1,038,336,253 1,009,237,702 532,678,090 458,128,950
Foreign Loan Repayment Debt Management wing 2,262,059,164 4,990,228,854 5,472,305,803 1,609,389,800 1,658,438,080
Repayment of Short- Term Foreign Credit Debt Management wing 47,874,926 29,500,000 199,810,000
Foreign Loans for Provincial Government Debt Management wing 454,364,336 617,000,000 774,953,280
Total 3,802,205,850 6,705,745,375 7,476,971,356 2,161,037,391 2,137,433,481
Page 64

5. Key Performance Indicator / Targets

Key Target Planned Medium Term Target
Outputs Performance Achieved Target
Indicators 2023-24 2024-25 2025-26 2026-27 2027-28
Foreign assistance, programming, negotiations, realization and management services and bilateral economic cooperation Estimates of Budget for providing management servicing 800,712,531 905,153,000 994,997,000 1,039,496,700 1,143,446,370
Contribution to International Agencies Organizations for membership Estimates of Budget for contribution 14,887,048,568 24,611,115,000 15,719,450,000 22,121,275,000 24,333,402,500
Capacity Building of the Nationals of Friendly countries National trained for long-term programme (Numbers) 344 485 485 485 485
Short term 29 50 50 50 50
Support to Temporarily Displaced Persons- ERP To strengthen recovery efforts and livelihood support to TDPs of affected areas. 1,800,282,902 5,125,000,000 5,100,000,000 - -
Foreign Debt Servicing Debt Management wing 1,020,401,885,158 - - - -
Foreign Loan Repayment of Principal Debt Management wing 2,262,059,163,509 - - - -
Repayment of Short- Term Policy Debt Management wing 47,874,925,690 - - - -
Foreign Loans for Provincial Government Debt Management wing 454,364,335,494 - - - -
Page 65

Power Division

PAO: Secretary 1. Goal: Develop the most efficient and consumer centric power generation system that meets the needs of its population and boosts its economy in a sustainable and affordable manner.

2. Policy: 3. Outcomes: 4. Budget by Outputs Rs. In ‘000

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Admin support /Policy development and approval /technical support Power Division 403,330 411,915 437,366 545,026 681,283
Reduction of electricity prices through provision of subsidies Power Division 975,184,377 681,000,000 636,136,000 1,210,000,000
Enhancement of electricity generation, transmission and distribution services National Energy Eff & Conservation Authority 230,000 228,000 89,525,783 564,514 705,642
Alternate energy support services National energy Conservation Centre 36,934 34,000 330,336 55,526 61,080
Total 975,854,641 681,673,915 726,429,485 1,211,165,066 1,448,005

5. Key performance Indicators/Targets:

Outputs Key Performance Target Achieved Planned Target Medium Term Target
Indicators 2023-24 2024-25 2025-26 2026-27 2027-28
Admin support /Policy development and approval /technical Reduction in average cost of generation (Rs/unit) EPP & CPP @ Rs.24.97 (EPP Rs.10.79) &CPP Rs. 14.18
support Collection of Government bill arrears (No. of outstanding arrears) 11,858,840,000
Reduction in circular debt (Rs million) Rs. 2.393 billion
Reduction in %distribution losses +1.48% .1%
Page 66

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Planned Capacity addition (MW) including hydropower 3177
Addition of Coal based power generation (MW) PPIB 2460
Implementation of Pakistan Energy Label Regulations 2023 Implementation of Energy Conservation Building code 2023 0.7 MTOE energy savings 3.5 MTCO2 emission mitigated Reduction of 50% energy demand in Energy Conservation Buildings Code (ECBC) complaint buildings. Building by laws amended and notified (Federal & Provincial) Building energy design Lab established Building rating system activated 0.03 MTOE energy savings 0.17 MTCO2 emission mitigated Development & approval of Energy conservation Building Codes (ECBC) 0.1 MTOE energy savings 0.3 MTCO2 emission mitigated Building energy design Lab established. 0.25 MTOE energy savings 0.8 MTCO2 emission mitigated Reduction of 50% energy demand in Energy Conservation Building Code (ECBC) complaint buildings. Buildings rating system activated. 0.5 MTOE energy savings 1.7 MTCO2 emission mitigated Revision of Energy Conservatio n Building codes (ECBC) 0.7 MTOE energy savings 3.5 MTCO2 emission mitigated Revision of Energy Conservation Building codes (ECBC)
On-bill Financing Scheme for Adoption of Energy Efficient Technologies Captive Units- Energy Saving Certificate Regime . On- bill financing scheme for 5 electrical appliances fully launched in domestic and commercial sector Concept Note Program development and consultation. On-bill financing scheme for FANS. Captive Units- Energy Savings Certificate issuance to top 5 most energy intensive consumers. On-bill financing scheme for LED lamps, refrigerators. Captive Units- Energy Saving Certificate issuance to top 10 most energy intensive consumers On-bill financing scheme for air conditioners and motors Captive Units- Energy Saving Certificate issuance to top 10 most energy intensive consumers
Development of National Electricity plan 1stNational Electricity plan (2023-27) approved 1stNational electricity plan developed & approved by the Cabinet 1stquarterly review completed 2ndfive-year National Electricity plan developed & approved by the Cabinet. 2ndfive-year National Electricity plan developed & approved by the Cabinet.
Page 67

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Enforce Anit- Electricity Theft Campaign for improving DISCOs recovery Monitoring & reporting of recoveries/ reduction in losses, legislation and improving enforcement mechanism Monthly reporting carried out regarding the recoveries, number of arrests, etc. Transaction Advisor engaged Pilot projects completed (2) HESCO & GEPCO; Bifurcation of LESCO & MEPCO; Operationalizati on of HAZECO Transition of DISCOs operations & managemen t through privatization, outsourcing and other modes. Transformer based metering deployed across all DISCOs
Transition of DISCOs operations & management through privatization, outsourcing, and other modes Privatization / outsourcing/ handover of 2 DISCOs completed. Roadmap developed to achieve 100% electrification target by 2030 Transition of DISCOs operations & management through privatization, outsourcing and other modes.
Universal National Electrification (UNE) Program Roadmap to achieve 100% electrification developed PIS developed and institutionalize d in PITC
Development of Power Information system (PIS) for integration, standardization and dissemination of sectoral data under a single platform PIS institutionalized PIS developed and institutionalized in PITC
Development of Green Hydrogen Policy for Pakistan - Pre-feasibility study -Inter- ministerial and inter- provincial. Formulation of working groups. Federal/provinc ial and state level. Draft of Green Hydrogen Policy Framework finalized. Implementati on of Green Hydrogen Policy.
Certification Regime for Energy Auditors and managers Regulations for Certification of Energy Auditors.& Managers finalized and approved Rules for energy audits of Designated Consumers formulated Baseline study to establish the energy consumption threshold for Designated Consumers Rules for energy audits ofDesignate d consumers finalized and approved by the Government mplementatio n of Regime for Certification of Energy Auditors & Managers and energy audits of Designated Consumers
Implementation of energy efficiency & conservation campaign for national behavioural change. Social print/ print Media. Energy Talks Consultation Podcasts Social print/ print Media. Energy Talks Consultation Podcasts Social print/ print Media. Energy Talks Consultation Podcasts Social print/ print Media. Energy Talks Consultation Podcasts . Social print/ print Media. Energy Talks Consultation Podcasts
Page 68

Petroleum Division

PAO: Secretary

1. Goal : To ensure availability and security of Oil, Development of Natural Resources of Energy and Mineral to cater energy needs of people of Pakistan.

2. Policy :

  • i. Pakistan Petroleum Exploration and Production Policy 2012. ii. LPG (Production and Distribution) Policy 2016. iii. National Mineral Policy 2013. iv. Low BTU GAS Pricing 2011/Tight GAS Policy 2011. v. Liquefied Petroleum GAS (Production & Distribution) Policy Guidelines, 2013.

3. Outcome : Impact on Target Population Availability of Oil and Gas to the people of Pakistan.

4. Budget by Output: Rs. In ‘000

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Carrying out geological surveys and development of information / database of Oil & Gas and natural resources Geological Survey of Pakistan 1,498,000 1,373,641 1,868,577 1,214,803 1,214,803
Enforcement of Mines Act & rules, regulations framed thereunder Mineral Wing 144,194 417,490 20,043 18,377 18,377
Formulation of laws and regulations regarding distribution and management of Gas and Oil including exploration and production of oil & Gas and other energy resources Policy wing/Directorate General Petroleum Concession, Gas and Oil 579,032 1,785,229 364,362 356,546 356,546
General Administration services and financial management Main Ministry 307,000 353,702 325,387 389,389 389,389
Research and Development in hydrocarbon Hydro-Carbon Development Institute 386,975 80,000 70,000 88,200 88,200
Explosive Management and regulatory services Department of Explosive 122,000 130,000 189,000 143,072 143,072
Provision of subsidy for providing gas on lower rate to industry (including Zero- rate export sector) 50,600,000 18,400,000 1,200,000 - -
Supply of Gas to special economic zones and other localities - 1,093,439 - - -
Total 53,637,201 23,633,501 4,037,369 2,210,388 2,210,388
Page 69

5. Key Performance Indicators/Targets:

Outputs Key Performance Indicators Target Achieved 2023-24 Planned Target 2024-25 Medium Term Target 2025-26 2026-27 2027-28
Carrying out geological survey Geological mapping (area in sq. 51,200 64,000 90,000 6400 6400
of and development of information Chemicals analysis of samples (number of samples) 1000 1000 1400 1000 1000
geological survey of Pakistan Geophysical surveys (number of studies) 6 6 12 15 15
Research studies for enhancement of scientific knowledge (number of studies) 10 6 7 7 7
Number of boreholes / depths for mineral investigation 7 5/1400 6/1400 6/1400 6/1600
Number of engineering geology studies 1 3 3 4 5
Enforcement of Mines Act & rules, regulations framed thereunder Mineral Number of inspections to be undertaken by central inspectorate of Mines 37 36 36 36 36
Wing Number of Training to be conducted by central inspectorate of Mines 18 12 12 12 12
Formulation of Laws and regulations Exploration/discovery of new oil, gas and coal fields 3D (sq.Km) 1351 2200 1800 1700 1600
regarding distribution and management of Exploration/discovery of new oil, gas and coal fields 2D (L.KMS) 2733 3500 3700 3800 3400
Gas and Oil Production rate oil per day (barrel) 70,524 72,747 66,406 61,557 58,706
Production rate Gas per day (mmcfd) 3116 3319 3403 3303 3293
Appraisal/development of wells (number0 37 40 40 35 38
Number of wells drilled (exploration) 22 27 35 30 32
Gas to be added in the system (BCFD) 1.189 0.29 0.41 0.48 0.66
LNG gas to be added in the system (BCFD) 1.046 1.032 1.032 1.032 1.032
Petroleum imports - Crude Oil million barrels 67.59 63.72 78.00 78.00 78.00
Page 70

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Petroleum imports others (million metric Ton) 0 0 0 0
Petroleum imports others (million metric Ton) 6.63 6.8 7 7.2 7.4
Capacity to refine oil- million 88.40 165 165 165 165
Research and Sample tested 14148 15102 15250 15400 15550
Development in Hydrocarbons Inspection of CNG Stations 194 290 292 295 300
HDIP Hydrostatic testing of storage and 10425 17200 17500 17800 18000
Explosive License renewed 11,697 11800 11850 11850 11850
management and regulatory services Revenue Targets in millions 599.490 1,125 800.08 825 850
Explosives Inspections conducted 8325 9000 9100 9200 9300
License Granted 2002 2000 2100 2150 2200
Vehicles Approved 2826 2900 2950 3000 3050
Layout GPL 364 400 425 450 475
Page 71

Federal Education and Professional Training Division PAO: Secretary

1. Goals: To ensure universal access to quality education through implementation in ICT and coordination with all provinces, regardless of gender, religion, or socio-economic background to implement SDG-4. This involves promoting both formal and nonformal education, as well as higher education, technical and vocational education, and religious education through conventional as well as distance learning modes. To improve the quality of teacher training, research, and assessment across all levels of education, from primary to tertiary.

2. Policy:

  • Development of the National Education Policy framework with clearly defined action plans.

  • Enhanced coordination among the federating units

  • Introduction of Distance Learning to provide learning facilities to the students of Class ECE to 12.

  • Increase in Skilled workforce across the country by providing vocational training.

3. Outcome:

  • E-Learning and digitization

  • Improved Learning outcome and reduced learning poverty

  • Enhanced level of learning through a modern infrastructure and professionally developed workforce

  • Significant decrease in the number of out-of-school children.

  • Increased Skilled workforce.

4. Budget by Output: Rs in ‘000

Outputs Office Ribl Actual Expenditure Budget Medium Term Budget
esponse 2023-24 2024-25 2025-26 2026-27 2027-28
Policy Management and Administrative Support Services Main Secretariat, Inter-Provincial Education Minister Conference, Inter Board Committee Chairman, P&D Units 807,663 8,423,135 3,490,703 5,883,564 5,883,564
Providing free education to children of Islamabad from Class I-X - Providing of free textbooks to approx. 250,000 students up to Class-X - Lighter bag initiative class (I-V) to protect health of children by providing additional set of textbooks in classroom - Continuous professional development of teachers to enhance the quality of education approx. 2,000 -Providing of free Federal Directorate of Education including 432 schools and colleges & AEO Offices 20,761,034 24,473,413 20,406,361 21,679,593 21,679,593
Page 72

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

transport to approx. 35,000 students up to class-X as well as subsidized transport to class XI & XII - ICT Schools and College Education Services
Grant, Contribution and scholarship to Local Students Main Secretariat 589,082 4,567,249 2,660,744 348,360 348,360
Compliance of International Commitments UNESCO 212,420 302,941 258,495 332,561 332,561
Promoting Relations in Education sector with China Pakistan Embassy China 51,322 57,457 57,457 63,211 63,211
Projection of Pakistan image and culture through Pakistan chairs Abroad Pakistan Chairs Abroad - 88,000 70,000 96,960 96,960
Home economics and management sciences education FG College home economics 76,466 78,559 85,756 86,504 86,504
Enrollment of girls in the fields of skill profession i.e., Commerce, Dress Designing & Making, Computer Information Technology, Architecture, Electronics and Office Management Polytechnic Institute and NISTE 149,651 151,659 147,057 166,974 166,974
Registration of Deni Madaris all across Pakistan - Introduction of Contemporary subjects in Madaris - Development of Data base of Deeni Madaris Directorate of Religious Education 423,762 25,000 70,782 27,472 27,472
Capacity Building of Managers, Teachers, Educationists etc. Pakistan Manpower Institute, National Talent Pool, National Training Bureau & Apprenticeship Training Centre 83,437 86,553 102,182 95,350 95,350
Providing Basic Education through Feeder Schools in ICT, GB and AJK Introduction of Contemporary Education in Marginalized communities (through Madaris) Enrollment of OOSC through Social Mobilization Capacity Building of Community Teachers NCHD 2,638,985 1,522,513 2,853,097 1,676,683 1,676,683
Page 73

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Pre-Service Teacher Education (Physical + Online) In Service Teacher Training and Education (Physical and Online) Federal college of Education 157,096 147,751 173,135 162,727 162,727
Provision of basic education through Community Schools in ICT, GB & AJK Establishment of ALP Centers Capacity Building of Teachers Provision of Teaching Learning Material Introduction of Blended learning in Community Schools Expansion of Schools through Public Private Partnership Quality assurance through Monitoring & Evaluation of BECS 841,106 883,872 934,440 971,453 971,453
Schools and Centers
Provision of Subsidized Education in Arts at Graduate/undergraduate level at Lahore, Rawalpindi, Islamabad & GB NCA 1,292,587 1,001,454 928,454 750,237 750,237
Personality Building of Youth Understanding Conservation of Environment Promoting personal safety among girls Improving International Exposure Pakistan Girl guides association 74,229 66,475 69,495 73,232 73,232
Life skill-based training
Regulating the fee of the private institutes Registration, Renewal & Regulation of Private Educational Institutions in ICT Monitoring and Evaluation of PEIs PIERA 57,730 36,740 36,740 40,483 40,483
Youth Activities including First Aid & Emergency Preparedness, Safe from Harm and SDGs), Adult Training, Membership Growth, Number of Pakistan Boy Scouts Association 48,153 43,155 43,155 47,505 47,505
Page 74

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Participants attending Youth Programmes
Development and publishing of textbooks as Federal Textbook Board Development and publishing of General books (fiction & non- fiction), children story books, braille books etc. Organizing books Exhibitions/Fairs across the country Supply of Books and reading material to other countries Awards on best books for children on Allama Muhammad Iqbal, Quaid- e-Azam and Pakistan National Book Foundation 120,604 120,604 120,604 132,884 132,884
Movement
Introduction of Digital Innovation in Education sector USF and Pilot Project for teaching grades 139,663 130,000 692,000 0 0
Strengthening Federal, Provincial Data Management Processes Publishing Yearly Pakistan Education Statistics (PES) Provision of Data to UIS on SDG-4 Capacity Building of National and Provincial EMISs Development of Open Data Portal Other Reports Conduct Qualitative/ Quantitative Research Pakistan Institute of Education 185,081 211,907 228,096 232,991 232,991
Surveys
Development of Standards and Model Text books for ECE-Grade 12 (including religious education) Development of Accelerated/Alternate Learning Program (for Madras, winter zone, multi- grade classrooms, out-of- school children, neuro- diverse children, etc.) Revamping Assessments Capacity Building of Teachers, Examiners etc. National Curriculum Council 113,787 0 0 0 0
Page 75
Approval of national distance education strategy Approval of the design and implementation plan of the distance learning, accelerated programs and formative assessment in lagging areas/districts Assessment of teacher training program up-take and potential impacts on pedagogical practice Implementation of a functional provincial and national open-source data platform Standardized data is collected, analyzed and publicly released for all provinces in the country Operationalization of item bank for national assessment and learning poverty comparisons Participation in an international assessment that includes competencies ASPIRE 10,928,396 8,875,780 0 0 0
in math and language
Broadcasting Tele school channel through TV, Radio and Mobile Application. Establishment of 4 channels through AIOU Development of new national early childhood distance learning content Distribution of 6000 Chromebook Communication Campaign through TV, radio, mobile and social media on education continuity and health boards Pandemic response effectiveness project, Response recovery and resilience in education programming in post-covid-19 579,458 0 0 0 0
Development of Institutions for care, education, training and rehabilitation of persons with disabilities 901,485 726,008 788,188 799,827 799,827
National Curriculum Development Prime Minister’s Scheme - 11,000 6,640,000 21,000 9,800,000 12,109 12,109
Page 76

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Pink Bus Initiatives - - 316,800 - -
ICT School & College Education Services (FDE) - - 1,010,641 - -
Implementation of a functional provincial and national open-source data platform Standardized data is collected, analyzed and publicly released for all provinces in the country - - 2,900,000 - -
Operationalization of item bank for national assessment and learning poverty comparisons Participation in an international assessment that includes competencies in math and language
"Participation in an international assessment that includes competencies in math and language Providing free education to children of Islamabad from Class I-X Providing of free textbooks to approx. 250,000 students up to Class-X Lighter bag initiative class (I-V) to protect health of children by providing additional set of textbooks in classroom Continuous professional development of teachers to enhance the quality of education approx. 2,000 Providing of free transport to approx. 35,000 students up to class-X as well as subsidized transport to class XI & XII ICT Schools and College Education Services" - - 2,504,407 - -
Delegation and contributions to International Organizations 155,000
Total 41,233,197 58,671,225 50,924,789 33,834,186 33,834,186
Page 77

5. Key Performance Indicators/Targets:

Outputs Key Performance Target Achieved Planned Target M id-Term Target
Indicators 2023-24 2024-25 2025-26 2026-27 2027-28
Policy Management and Administrative Support Services Making ministry and attached departments more efficient, effective and responsive to citizen (Number of complaints) 19 18 18 18 18
Management of PSDP Projects (number) 24 18 20 20 20
Projection of Pakistan image and culture through Pakistan Chairs Abroad 14 Pakistan Chairs Abroad (Number of chairs at foreign universities) - 3 5 8 10
Holding of National and International Events Inter Provincial Education Ministers Conference, other events. (numbers) 1 5 5 5 5
Introduction of Digital Center of Excellence - 1
Innovation in Education sector Establishment of School for tomorrow 10 20 30 40
Development of Standards and Model Text books for ECE- Grade 12 (including 40 Policy Dialogues (for stakeholder engagement) in all federating units / regions (numbers) 8 8 0 0 0
religious education) 24 in-person NCC Workshops for capacity building, Curriculum Workshops (IPCWs), 8 for academic/technical work and 10 internal review workshops of model textbooks (number of workshops) 8 10 0 0 0
5 Rounds of Feedback collection and incorporation through online portal (numbers) 1 1 1 1 1
20 Regional Curriculum Workshops (RCWs) in the federating units/regions (number of workshops) 8 4 7 7 7
10 field visits for research and analysis of current situation (number) - 2 2 2 2
Textbooks developed [Grades 1 - 12] for Religious Education for 7 minority faiths (number) 21 49 7 7 15
56 model number textbooks titles 26 10 10 10 10
Page 78

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

developed for ECE to Grade 8 (No)
Teacher's Development . Number of Policy dialogues across Pakistan to gather feedback 8 8 8 8 8
Number of Teacher Training Manuals (TTM) Development [ECE - Grades 12] 8 8 9 9 9
Regional workshops for Continuous Professional Development Framework development and finalization - 8 7 7 7
Number of TTMs (documents and associated resources) developed and approved by experts & provinces - 8 6 8 8
Revamping Assessments 16 Policy Dialogues in all Provinces/Federating Units (numbers) 8 8 8 8 8
26 Assessment Frameworks for all subjects (ECE-5) (number) 9 0 6 6 6
Development of 33 Teacher Training Modules for the core subjects (ECE-5) (number) - 11 6 6 6
Development of Assessment Frameworks of Religious Education 20 11 3 1 1
16 training workshops of examiners, teachers etc. - 8 6 2 2
Broadcasting Tele school channel through TV, Radio and Mobile Broadcasting Tele school channel through TV (number of programs) 12
Application. Number of Dissemination of national distance learning content on Mobile Application 1
Broadcasting distance learning content through Radio 8
Sustainability of Tele school initiative through AIOU Establishment of 4 digital channels
Development of Distance Learning Content Development of distance learning contents from ECE to 12 (number)
Establishment of Smart Classrooms Establishment of 200 smart classroom in Federal Areas
Page 79
E-Taleem Portal Establishment of E- Learning Solution through Mobile App / Web Portal including Virtual Teacher Training Module (number)
Communication Campaign through TV, radio, mobile and social media on education continuity and health Reach 1.2 million people through communication campaign on education continuity and health (number)
Distribution of Schools on wheels for flood affected areas Distribution of 34 busses as school on wheels in the flood effected areas of Pakistan (number)
Distribution of learning materials including books, worksheets and smart boards Distribution of learning material in 9000 schools all over Pakistan (number of schools) 9,000
Distribution of 300 smart boards on lagging districts of Pakistan (number) 300
Gender Analysis Needs assessment for female well-being and health during and post COVID-19- Need assessment. Parent Surveys to assess satisfaction of project interventions implemented (number of survey) 1
Review of existing assessment framework and designing of inclusive distance learning competency standards. Hiring consultancy to carry out review of existing framework (number) 1
Creation of pathway for Certification of Distance Learning Programs at national level and design mechanism for integration of OOSC into the mainstream education system Hiring consultancy to carry out Certification of distance learning programs (number) 1
Procurement and distribution of basic sanitization and hygiene supplies to public schools for safe school reopening Distribution of hygiene kits in 12000 schools of Pakistan 12,000
Implementation of teacher professional development programs to address learning Execute teacher training in all the lagging districts of Pakistan (number of trainings) 12,500
Page 80
gaps including training of targeted number in priority areas
Establishment of Computers Lab in ICT Upgradation of Computer Labs in ICT Schools 5 30
and Distribution of Chromebooks Distribution of 6000 Chromebooks 6,000
Multimodal programs in lagging areas/districts Up to 20,000 students enrolled in multimodal programs in lagging areas/districts (number of students) 75,852 5,000
Approval of national distance education strategy Approval of national distance education strategy (number) -
Students received distance learning kits Up to 50,000/year Students received distance learning kits (number of distance learning kits) 2,430,687 50,000
Distribution of cleaning kits At least 20,000/year public schools received cleaning kits (number of cleaning kits) 64,197 50,000
Construction/rehabilitati on of Classrooms Up to 2,500 classrooms built /rehabilitated (number of classrooms) 652 500
Schools attended by girls with rehabilitated WASH facilities Up to 1,000 schools attended by girls with rehabilitated WASH facilities (number of schools) 361 500
Expanding connectivity for education in at least lagging areas/districts Free public WiFi access points and subsidized access to educational connectivity programs, in lagging districts (number of WiFi access points) 496 2,000
Communication Campaign Number of children, teachers, and parents reached with sensitization campaigns for education and mental health wellbeing 17,000,000 2,000,000
Number of children reached with back-to- school sensitization campaigns and behavioral nudges, focusing on girls and marginalized groups 218,526 5,000
Design and implementation plan of the distance learning, Approval of the design and implementation plan (number of plan) 1
Page 81

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

accelerated programs and formative assessment in lagging areas/districts Number of students benefiting from new accelerated learning programs in lagging areas/districts 12,302 20,000
Teacher training program up-take and potential impacts on pedagogical practice Teacher training program up-take and potential impacts on pedagogical practice 3,605 20,000
Distance Learning Coaching Program 500 4,000
Tablets, solar chargers with internet connectivity; and supplementary materials received by teachers 13,643 5,000
The National Equitable Education Program (NEEP) Budget of at least $30,000,000 equivalent is approved, allocated and released Allocation of Budget and transfer to provinces 1 1
to provinces
Provincial and national open-source data platform Implementation of a functional provincial and national open-source data platform (number) 1
Item bank for national assessment and learning poverty comparisons Operationalization of item bank for national assessment and learning poverty comparisons (number) 1
Data is collected, analyzed and publicly released for all provinces in the country Standardized data is collected, analyzed and publicly released for all provinces in the country 1 1
Providing free education to children of Islamabad from Class I- X Number of students being provided Free Education, including free textbooks (Class 1-10) 210,000 210,000 210,000 215,000 215,000
Providing of free textbooks to approx. 250,000 students up to Class-X Number of students being provided subsidized education at HSCC Level 28,991 29,000 30,000 31,000 31,000
Lighter bag initiative class (I-V) to protect health of children by providing additional set of textbooks in classroom Number of students being provided subsidized education at Bachelors of Science/ Associate Degree Program Level 6,727 8,000 9,000 10,000 10,000
Centralized biometric attendance system to ensure regularity and punctuality. Implementation of HRMIS for effective management, monitoring and supervision (number) 13,000 13,500 13,600 13,800 13,800
Continuous professional development of Increased Pass Percentages SSC 100% 100% 100% 100% 100%
Page 82

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

teachers to enhance the quality of education approx. 2,000 Increased Pass Percentages HSSC 100% 100% 100% 100% 100%
Providing of free transport to approx. 35,000 students up to class-X as well as subsidized transport to class XI & XII Number of Institutions to be maintained 432 432 432 432 432
ICT Schools and College Education Number of students to be enrolled 250,000 255,000 260,000 265,000 265,000
Services
Policy Management and Administrative Support Upgradation of Computer Labs in ICT Schools 16 20 30 40 40
Services Outsourcing of Phsycologists in School for dyslexia 50 50 50 50
Procurement of Internet Licensing in no. of schools/ colleges 50 50 50 50 50
Introduction of Meal Programs in Schools No. of Institutions in which meal program introduced 192 192 250 350 350
Provision of Sports Revamping of Grounds 100 200 300 300
Facilities to Students Distribution of Sports Kits in Schools/ Colleges 200 300 400 400
Inter Colleges Sports Competitions 1 1 1 1
Providing Basic Number of Community 345 345 345 345 345
Education through Feeder Schools
Feeder Schools in ICT, GB and AJK Teachers Training on Non-Formal 434 434 434 434 434
Enrollment 13641 14,500 14,500 14,500 14,500
Male 7072 7,540 7,540 7,540 7,540
Female 6569 6,960 6,960 6,960 6,960
Introduction of Number of Contemporary 100 100 100 100 100
Contemporary Education Centers
Education in Capacity building of 120 120 120 120 120
Marganilized Teachers & Field officers
communities (through Enrollment 2165 2,581 2,581 2,581 2,581
Madaris) Male 1801 2,100 2,100 2,100 2,100
Female 364 481 481 481 481
Community School for basic education Enrollment of out of school’s children age (5- 9) years and their mainstreaming through 1225 community schools 60364 61,750 64,923 68,117 68,117
Alternative Learning Program Centers Enrollment of out of school’s children (OOSC) age (9-16) years for completion up to class V within 30 months and their mainstreaming 1399 57 57 57 57
Male (49%) 29622 (49%) 30,283 31,838 33,390 33,390
Page 83

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Female (51%) 30742 (51%) 31,467 33,085 34,727 34,727
Enrolment rate (Number) Maximum OOSC will be enrolled -
Compliance of International Commitments Contribution to International Agencies & Organizations (Number) 1 2 2 2 2
Holding of KNIKKE Festa, ASP Network workshops, event etc. 5 8 8 8 8
Promoting Relations in Education sector with China Number of Students enrolled 1,500 2,000 2,500 3,000 3,000
Provision of Subsidized Education in Arts at Enrolment of Batch (number) 1766 933 961 990 990
Graduate/ Male 693 469 483 497 497
undergraduate level at Female 1073 464 478 493 493
Lahore, Rawalpindi, Passed out Graduates 313
Islamabad & GB Male 104
Female 209
Personality Building of Youth (PGGA) Promoting Better Citizenship (Developing Patriotism, Road Safety, Emergency Preparedness/First Aid, Understanding Right & Responsibilities) 15200 18,000 20,000 23,000 23,000
Developing Leadership Skills (Decision Making, Practicing Democracy, Team Building) 5300 6,000 7,000 8,050 8,050
Promoting Personal Development (Creativity, Intelligence, Skills) 8000 8,500 9,000 10,350 10,350
Promoting Better Health Practices (Personal Hygiene, Health & Nutrition, Promoting Healthy Lifestyle) 11098 12,000 15,000 17,250 17,250
Promoting better Interpersonal Skills (Promoting Peace & Harmony, Conflict Resolution, Understanding Diversity, Communication Skills) 8311 9,000 10,000 11,500 11,500
Enhancing Wellbeing & Self Esteem (Emotional Wellbeing, Enhancing Confidence of Girls regardless of physical attributes) 7150 7,000 7,500 8,625 8,625
Page 84

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Promoting Outdoor activities (Camps, Hikes, Games etc.) National Celebrations 15300 11434 17,000 12,000 19,000 15,000 21,850 17,250 21,850 17,250
Promoting personal safety among girls (PGGA) Awareness Campaigns 20220 19,500 20,000 23,000 23,000
Promoting International International Badge 10114 12,000 15,000 17,250 17,250
Dimensions (PGGA) holders
Life skill-based training (PGGA) Training of School Teachers and College Lecturers 1597 1,700 1,900 2,185 2,185
Training of Trainers & Staff 67 60 60 69 69
Training of Volunteers 169 180 200 230 230
Number of Participants National Youth Forums 2000 1,300 1,400 1,500 1,500
attending Youth National Snow & Desert 207 350 400 430 430
Programmes (Youth Hikes
Activities including First SDGs Boot Camp 260 135 140 150 150
Aid & Emergency National Scout Week 900 600 665 700 700
Preparedness, Safe Seerat Conferences 403 160 170 190 190
from Harm and SDGs) Scout Gatherings and Awareness Campaigns 626 320 340 380 380
World Scout Environment Programme (WSEP) including Tree Plantation, Climate Change and Tide Turner Plastic Challenge 1500 1,300 1,350 1,420 1,420
Inter Cadet Colleges & other competitions 130 160 170 190 190
Skilled Learning Camps 406 320 340 380 380
Leader Courses and Workshops for Scout Leaders including 478 370 390 430 430
Adult Training (PBSA) trainings of Rescuers of 1122, officials of private institutions (No. of participants)
Initiative for inclusion of Private Educational Institutions in the 750 270 290 330 330
Membership Growth (PBSA) scouting stream, gatherings for online registration of scouts at National/Provincial and District Level Meetings
Grant, Contribution and scholarship to Local Students Number of Scholarship to Indian Occupied Kashmir. 100 100 100 100 100
Large Scale Educational National and International Assessment for Policy Decision (PIE) Reporting of Educational Proficiency on student learning achievement in the subject of Mathematics, Science and Languages at Grade 4 & 8 level 1 - - - -
Page 85

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Participation in International Assessment for Establishment of International Benchmark of Pakistan in Numeracy and Literacy 1 - 1 - -
Capacity Building of Human Resource on Global Proficiency Frame Work (GPF). Test item Development and Formation of National Assessment Frame Work. 30 24 24 - -
Strengthening Federal, Provincial Data Management Processes (PIE) Consolidation of Education data from Public, Other Public Private, Non-Formal, Deeni Madaris, Colleges, Higher Education Commission, Education Foundation, Technical & Vocational Education from provincial/area EMISs 1 1 1 1 1
Technical/Coordination Committee Meetings of Provincial/areas EMISs 2 2 2 2 2
Computation of Education Indicators based on NEMIS database 1 1 1 1 1
Publishing Yearly Pakistan Education Development of PES Report 3 1 1 1 1
Statistics (PES) (PIE) Data/Time Series Analysis 3 1 1 1 1
Dissemination of Report 3 1 1 1 1
Provision of Data to UIS on SDG-4 (PIE) Inputs for the transformation in national education system 1 1 1 1 1
Transformation of Data to ISCED levels 1 1 1 1 1
Submission of Data on prescribed questionaries to UIS. 1 1 1 1 1
Capacity Building of National and Provincial SDG-4 thematic Indicator Framework 50 50 50 50 50
EMISs (PIE) Regional Benchmark 50 50 50 50 50
Data Visualization and Analytics 1 50 50 50 50
Education Indicators - 50 50 50 50
Development of Open Data Standardization - 1 1 1 1
Data Portal (PIE) Framework Data Integration - 1 1 1 1
Page 86

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Third party validation of Data - 1 1 1 1
Other Reports (PIE) Pakistan Education Atlas - 1 1 1 1
District Education Profile - 1 1 1 1
Conduct Qualitative / Quantitative Research Surveys (PIE) Conduct Qualitative/Qualitative Research Surveys on the Policy themes identified by the MOFEPT. - 1 1 1 1
Publication and Dissemination of Research Reports with Federal/Provincial/Areas stakeholders for policy improvement/ formulation & educational interventions - 1 1 1 1
In Service Teacher Training and Education (Physical & Online) Establishment of National Institute of Excellence in Teacher Education (NIETE) at FCE for monitoring teacher performance - -
Train all teachers in new pedagogy and digital literacy - 10,000 - - -
Enrollment of girls in the fields of skill profession i.e., Commerce, Dress Designing & Making, Computer Information Technology, Architecture, Electronics and Office Technical /Skilled Education (number of female students enrolled) 428 750 750 750 750
Management
Registration, Renewal & Regulation of Private Educational Institutions Inspection of Private Educational Institutions (Numbers) 250 280 300 310 310
in ICT Qualitative Assessment Report (numbers) 230 250 280 295 295
Registration of Private Educational Institutions (PEIs) (Numbers) 230 250 280 280 280
Renewal of PEIs (number) 900 950 1,000 1,050 1,050
Monitoring of PEIs 300 350 350 350 350
Registration of Deni Madaris across Registration of Madaris (numbers) 18,043 - Project Closed Project Closed Project Closed
Pakistan Enrolment of teacher in Madaris for imparting contemporary Education. 1196 - Project Closed Project Closed Project Closed
Provision of Books to Students Enrolled in Madaris 102,600 - - - -
Page 87

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Implementation of National Curriculum in Madaris (numbers) 163 - - - -
Facilitation of foreign students by helping them in obtaining and extension of Pakistani Visa (numbers) 1,609 - - - -
Paigham-e-Pakistan Seminars (numbers) 40 - - - -
Recreational activities like conferences, fairs, exhibitions, and other national celebrations (numbers) 8 - - - -
Development and publishing of textbooks as Federal Textbook Board Developed and published textbooks and general books at moderate prices 161 150 160 170 170
Development and publishing of General books (fiction & non- fiction), children story books, braille books etc. Development and publishing of General books (fiction & non- fiction), children story books, braille books etc 164 180 190 210 210
Organizing books Exhibitions/Fairs across the country Promotion of reading habits and books culture (number of exhibition) 323 240 240 250 250
Supply of Books and reading material to other countries List of Scheme to create soft image of Pakistan, art, values etc. in all over the world 360 450 465 470 470
Awards on best books for children on Allama Muhammad Iqbal, Quaid-e-Azam and Pakistan Movement No. of awards to best books for children 11 14 16 16 16
Development of Institutions for care, education, training and rehabilitation of persons with disabilities and social welfare services Rehabilitation of persons of disabilities (PWDs) by DGSE 3514
Training and rehabilitation of PWDs by DGSE 23285
Education and Rehabilitation of PWDs by DGSE 3200
Library Services by DGSE (No. of Persons) 4382
Page 88

Higher Education Commission

PAO: Executive Director

1. Goals: To enhance the capacity of higher education institutions to plan and reform standards-based tertiary education systems in Pakistan, thereby contributing to the development of a competitive knowledge-based economy.

2. Policy: Increase opportunities for equitable access to higher education, faculty development and quality enhancement, technology infusion, Research, Innovation & Commercialization, and modernization of curricula with introduction of new academic programs in emerging fields.

3. Outcome: Improved access and better quality of higher education can lead to development of skilled workforce, which in turn can have a significant impact on socio-economic well-being of the country.

4. Budget by Outputs: Rs. In ‘000

Ott Actual Expenditure Budget Medium Term Budget
upus
2023-24 2024-25 2025-26 2026-27 2027-28
Enhance the Equitable Access to Higher Education 45,699,055 62,169,364 38,992,849 31,151,591 31,151,591
Enhance Quality of Higher Education, Outcome-based Learning and Use of Innovative Modes of Delivery 30,003,674 32,274,738 24,159,985 16,172,104 16,172,104
Increase Faculty with Highest Academic Qualifications and Professional Skills 16,058,314 13,416,768 14,589,208 6,722,824 6,722,824
Promote relevant Research, Innovation & Commercialization 14,350,309 12,491,431 14,126,021 6,259,159 6,259,159
Strengthen Leadership, Governance and Financial Management in Higher Education 6,772,779 12,294,149 14,027,269 6,160,306 6,160,306
Total 112,884,130 132,646,450 105,895,336 66,465,985 66,465,985
5. Planned and Delivered key Performance Targets
Outputs Key Performance Indicators Target Achieved 2023-24 Planned Target 2024-25 Medium Term Target 2025-26 2026-27 2027-28
Enhance the equitable access to Higher Education Total Number of students benefiting from Financial Aid Program (HEC - Need Based scholarships) 23,750 26,184 27,493 28,868 28,868
Page 89

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Fully funded scholarships for Indigenous Undergraduate / Masters / MPhil students of FATA and Balochistan Phase II & III 3,039 3,939 4,900 5,410 4,800
Law Graduates Scholarship Program for students from Balochistan to Study Abroad- HEC 70 80 75 50 50
Undergraduate Scholarship Program for the Students of Gilgit-Baltistan in Top Public Sector Pakistani Universities 260 235 - - -
Coastal Region Higher Education Scholarship Program for Balochistan (New) 30 100 150 188 155
Total enrolled students in all Universities/Degree Awarding Institutions 2,269,186 2,374,186 2,484,186 2,599,186 2,719,186
Total Number of Universities/Degree Awarding Institutions in higher education sector (public +private+distance) 268 270 272 274 276
Enhance Quality of Higher Education, Outcome-based Learning and Use of Innovative Modes of Delivery Total Number of Ph.D. Faculty in Universities / Higher Education Institutions 23,096 24,196 25,296 26,396 27,496
Total Number of Academic Programs Accredited by all Accreditation Councils 2,759 2,909 3,059 3,209 3,359
Number of Higher Education Institutions annually reviewed for PhD Programs 13 20 20 25 30
Number of Curriculum annually reviewed and aligned with outcome- based- learning 12 25 13 10 7
Total Number of Higher Education Institutions transformed into Smart Campuses 106 114 122 130
Smart Universities Transformation through Smart Classroom 100 170 210 235 285
Total Number of Higher Education Institutions 451 500 535 575 600
Page 90

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

provided Pakistan Education Research Network (PERN) connectivity and digital resources
Increase Faculty with Highest Academic Qualifications and Professional Skills Number of PhDs produced by Higher Education Institutions, annually 2,698 2,880 2,925 2,970 3,015
Number of faculty provided trainings including Pedagogical Skills, annually. 513 100 120 150 200
Number of Fully Funded Overseas PhD Scholarships - 1,013 985 898 766
Number of Indigenous Ph.D. Scholars provided International Research Exposure (6- Months training), annually 270 279 300 350 400
No. of annual Postdoctoral Fellowships (Phase-III) 14 25 90 90 90
Promote relevant Research, Innovation & Commercialization Capacity Building Workshops for editors of research journal 7 7 7 7
Number of Competitive Research Grants awarded under National Research Program for Universities (NRPU) 25 30 35 40
Number of National Research Centers established in universities - 5 5 - -
Number of Business Incubation Centers annually established in HEIs 3 02 02 02 02
Number of Startup / Companies incubated in Higher Education Institutions 797 850 900 950 1,000
Number of Startups / Companies graduated from Business Incubation Centers at HEIs 603 600 650 700 750
Page 91

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Number of Research Support Grants to MS/M.Phil/PhD students under ASIP (Access to Scientific Instrumentation Program) 300 100 100 100 100
Number of awards Under HEC Best Research Awards 7 9 9 9 9
Number of Travel grants Awarded to Faculty and MS/ MPhil Students at HEIs 132 190 195 200 210
Number of Grants for Conferences, Seminars, Symposium & Workshops at HEIs 61 66 71 76 81
Number of ORICs Established at HEIs 6 3 3 3 3
Strengthen Leadership, Governance and Financial Management in HE Sector Number of Universities assessed as per Institutional Performance Evaluation Standards (IPES), annually - 10 15 20 30
Number of university administrative and academic leadership provided local and foreign trainings 38 50 60 65 75
Number of universities implementing standardized Double Entry Accounting System (DEAS) 55 60 70 75 80
Page 92

National Vocational and Technical Training Commission PAO: Executive Director

1.Goal: To facilitate, regulated and provide policy direction for Vocational and Technical Training of the unskilled workforce

2.Policy:

  • (i) NAVTTC Act 2011

  • (ii) Revised NAVTTC Act 2021 (iii) National "Skills for All" Strategy 2018 (iv) NAVTTC Service Regulations

3.Outcomes:

4.Budget by Outputs Rs. In ‘000

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Governance of TVET Sector (non- development expenses) Finance wing 1,032,316 716,059 1,147,013 1,161,974 1,278,171
Capacity building through skill development Finance Wing 4,392,915 6,417,120 4,900,000 9,200,000 11,050,000
Total 5,425,231 7,133,179 6,047,013 10,805,742 12,328,171

5.Key Performance Indicators/Targets:

Outputs Key Performance Indicators Target Achieved 2023-24 Planned Target 2024-25 Medium Term 2025-26 2026-27 Target 2027-28
Governance of TVET Sector (non- development Digital E-Learning contents development (LMS, CMS simulations etc.) (Qualification Digitalization) 50+ 50 60 80 10
expenses National Skills Information system software (Joint Skill Verification) 15,000+ 15,000 25,000 25,000 10,000
Implementation of RPL Policy (Certificate under NVQ5) 11,184 10000 12500 15000 20000
Capacity Building for Recognition of Prior Learning (RPL) (Persons) SVP 2166 (Assessors trained on CBT &A model) 1000 1000 1000 1000
Training of Trainers (ToT) CBT 409 1000 1000 1000 1000
Page 93

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Accreditation of TVET institutes-Remuneration of Assessors/Experts 79 200 400 500 500
TVET accreditation and quality evaluation committee 3 4 8 8 8
Capacity Building/Trainings of 765 Assessors on new manual NIL 365 765 765 765
BMR lumps grants for best TVET institutes NIL 4 10 10 10
Monitoring and Evaluation of the institutes 1,080 1000 1200 1400 1600
PMS Portal (Job placement portal, tracer studies and demand supply analysis 1 1 1 1 1
Unforeseen expenditures for implementation of NAVTTC BoM initiatives - 0 0 0 0
Attestation /verification of TVET Sector Certificates for Quality Assurance System (No). 4750 1,500 1,500 1,500 1,500
Capacity Building through Skill development Training under PM’s youth skill development program. 60,324
PMS Portal Job placement, tracer and demand supply analysis 0 1 1 1 1
Unforseen expenditure for implementation of NAVTTC BoM initiatives NA NA NA NA NA
Outcome based skill funding 250 400 750 1000 1500
TLM / Question bank / Validation and review 70 100 120 140 160
On-going Projects Introducing Matrictech Patch ways integrating technical training and formal education
Prime-Minister’s special package to implement skils for all strategy as a catalyst for all TVET sector development in Pakistan Ongoing development program
Page 94
PM Youth skill development
23-24
Skill Dev program NAVTTC
Page 95

National Heritage and Culture Division PAO: Secretary

1. Goal: Preservation & Promotion of National History, tangible and intangible Heritage and promotion of Literary Heritage, National & Regional languages and develop common values of arts and culture.

2. Policy: National Heritage and Culture Policy (Under process)

3. Outcome: To spread the vision and ideas of Quaid-i-Azam & Allama Iqbal and projection of Iqbal's message through research, IT products, books and exhibitions. Promotion & protection of tangible & intangible heritage of Pakistan. Promotion of Book culture, promotion of Urdu and regional languages. Exploration of archeological sites, preservation and presentation of antique artifacts. Financial assistance and welfare of writers and bereaved families.

4. Budget by Outputs:

Actual Budget Medium Term Budget
Outputs Office Expenditure
2023-24 2024-25 2025-26 2026-27 2027-28
Research guidance & academic assistance to the researchers through publication of Jinnah papers & Other Publications. Quaid-i-Azam Academy & Sub Office 31,271 31,000 44,000 52,275 57,503
Repair, Maintenance and Security of Quaid's mausoleum and its allied building and security arrangements. Quaid-i-Azam Mazar Management Board, Karachi. 209,052 108,000 415,000 405,464 446,010
Projection of Iqbal's Message through, Research, Books, IT Products & Exhibitions. Iqbal Academy Pakistan, Lahore 93,943 76,000 1,094,073 193,152 212,467
Carry out archeological survey for documentation of archeological sites and historical monuments under Antiquities Act 1975.sss Department Of Archeology, National Museum of Pakistan and Islamabad Museum, Islamabad. 388,133 200,000 389,074 414,072 455,479
Policy Formulation, Administration and Implementation of International agreements. Main Secretariat, ICP, Imp. of Agreement & Assistance and International Contributions and Development of 371,287 876,347 888,102 991,262 1,189,514
Page 96

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Heritage & Culture and Archeological sites Improvement.
Printing & Publication of official material, books in the field of science and compilation of dictionaries in Urdu language. * National Language Promotion Department, Urdu Science Board and Urdu Dictionary Board 287,286 129,000 398,000 410,210 446,315
Printing & publication of different books of literature, translation of mystic poets and promotion of national & regional languages. Pakistan Academy of Letters, Islamabad. 201,280 132,000 156,000 300,489 330,537
Provision of stipend to Writers and financial assistance to learned bodies. Pakistan Academy of Letters, Islamabad. 149,859 14,886 165,000 408,784 449,663
Library Services National Library of Pakistan and Subscription to International Organizations 140,400 96,290 130,450 169,895 203,750
Arts & cultural activities through various arts councils, academies & encouragement of artists, artisans & folk performances. Pakistan National Council of Arts (PNCA), Lok Virsa and National Academy of Performing Art (NAPA). 681,465 417,000 492,000 1,353,319 1,668,339
**Total ** 2,553,976 **2,294,684 ** 4,171,699 4,698,922 **5,459,637 **

5. Key Performance Indicators/ Targets:

Outputs Key Performance Indicators Target Achieved 2023-24 Planned Target 2024-25 Medium Term 2025-26 2026-27 Target 2027-28
Research guidance & academic No. of beneficiary (Researchers & Students) 2900 2250 3260 4260 5280
assistance to the researchers through publication of Jinnah No. of books to be published (Jinnah Paper and Quotes) 2 1 1 1 1
papers & Other Number of books (fresh) 1 1 1 1 1
Publications. Number of books (reprint) 1 2 2 2 2
Repair, Maintenance and Security of Quaid's museum and its allied building and security arrangements. Number of Visitors to be increased through Promotions/Maintenance 1.94 million 1.900 million 1.950 million 2.000 million 2.050 million
Page 97

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Projection of Iqbal's Message through No. of website visitors (million) 11.19 Million 10.00m 10.50m 11.0m 11.50m
, Research, Books, IT No. of beneficiary 15,847 15000 15000 17500 18000
Products & No. of Books (Reprint) 3 40 50 60 65
Exhibitions. No. of Books (Fresh) - 40 50 60 65
IAP multimedia products (Audio Video Compilation of Iqbal) (Numbers) 351 3 4 5 6
No. of Iqbal Awards of Best Books - 6 3 1 1
Carry out No. of archaeological site 20 15 - - -
archeological survey to be explored
for documentation of archeological sites and historical monuments under Antiquities Act 1975. No. of artifacts preserve and presented in the Museum. 1610 2000 2500 3500 4500
Policy Formulation, Administration and Implementation of International agreements. No. of Troupes in the field of Heritage & Literature 2 3 3 3 3
Printing & Publication of official material, books in No. of lectures/seminars to be conducted on scientific topics. 3 20 20 20 20
the field of science and compilation of dictionaries in Urdu No. of books to be published in the field of science 5 16 16 16 16
language No. of Books in Urdu Language (NLPD). 08 19 8 8 8
Concise dictionary (No.) 1 1 1 1 1
Printing & publication of different books of literature, translation of mystic poets and promotion of national No. of Books, Periodicals, Annual Bibliography, Monthly Newsletters and English Journals to be published on Literature. 20 27 30 34 35
& regional languages No. of Literary Programs/Seminars 275 120 125 135 140
Provision of stipend to Writers and financial assistance No. of Beneficiaries (stipend to Writers & bereaved families) 960 1000 1000 1000 1000
to learned bodies. No. of Academic, Kamal- e-Fun awards to writers 42 1 1 1 1
No. of Beneficiaries of Literary Bodies 35 33 36 36 36
No. of writers receiving lump sum financial assistance 10 50 60 60 60
Group Insurance (No. of writers) 1,000 1000 1000 1000 1000
Library Services No. of Books. 12,000 12000 12000 12500 13000
Volumes of periodicals (No.) 1,800 1800 1800 1800 1800
Page 98

Medium Term Performance Based Budget FY 2025-2026 to 2027-28

Publications of national bibliography (No. of Volumes) 1 1 1 1 1
ISBN registration numbers/library membership. 5,120 5000 5000 5500 6000
No of trainings for librarians 12 12 12 15 18
No. of Libraries (DOL) - 0 0 0 0
No. of visitors in Libraries 72,910 70000 80000 90000 95000
Arts & Cultural activities through various arts councils, academies & encouragement of artists, artisans & folk performances. No of activities 2 5 5 5 5
Page 99

National Rehmatul-lil Aalameen Authority PAO: Director General

1. Goal: The goal of NRKNA, in medium term and long-term context, is to promote research in practical and theoretical aspects of Seerat of Holy Prophet (PBUH) for addressing contemporary social challenges and inculcating positive changes in the Pakistani Society while providing illustrations about the life of the last Holy Prophet (PBUH).

2. Policy: The Policy direction of NRKNA is oriented towards following avenue in upcoming five years: i. Provision of guidance framework for the young generation on key and multifarious aspects from the life of the Holy Prophet (PBUH)

  • ii. Building linkages with provincial governments and prominent illustrations working on the Seerat.

  • iii. Establishment of the Seerat chairs in Higher Education Institutions.

  • iv. Formulation of strategies and frameworks for organizing impactful events to promote lessons from the seerat-eTayyabba.

3. Outcome: The NRKNA is aimed at the provision of following outcomes:

  • i. Development of collective conscience based on the teachings of Holy Prophet (PBUH) to reinvigorate national vibrancy and resilience.

  • ii. Promotion of framework of virtue and spirituality in the society as prescribed by last Holy Prophet (PBUH).

  • iii. Awareness to the youth of Pakistan regarding various aspects of Seerat to strengthen their moral and intellectual rectitude.

4. Budget by Outputs: Rs. In 100’

Outputs Office Actual Expenditure 2023-24 Budget 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Formulate Policies, Strategies and interventions to advance and propagate key elements of the Life of Holy Prophet (PBUH) Rahmatul-lil Aalameen Authority 79,578 101,751 110,997 547,389 625,371
Total 79,578 101,751 110,997 547,389 625,371
Page 100

5. Key Performance Indicators/Targets

Outputs Key performance Indicators Target Achieved 2023-24 Planned Target 2024-25 Medium Term Budget 2025-26 2026-27 2027-28
Research, Publications and Seminars 1. Publication of Annual Research Journal contemporary scholarly research on the seerat of Holy Prophet (PBUH) 2. Holding of Annual Research Symposium premised around thematic talks and publication presentations 3 3 3 3 3
Creation of Linkages with International Institutions working in the domain of Seerat Nabwai 1.At least 5 Domestic instruments of cooperation 2. At least 5 int. instruments of cooperation 3. Quarterly performance report on external linkages 4. Initiation of Exchange program of Scholars/faculty/stude nts 1 1 2 2 2
Development of Curriculum based on the teaching of Holy Prophet (PBUH) Production of Draft Report and stakeholder consultation on Minimum learning standards in the context of Seerat e Nabvi 1 1 1 1
Establishment of National Volunteer Program Finalization of project proposal on NVP 0 1 1 1
Documentaries and production of other electronic and digital content to disseminate the message of Holy Prophet PBUH Production and dissemination of expository documentary 2 3 3 1